Filings for 48583
Case Style COMPLAINT OF MCCORD DEVELOPMENT, INC. AGAINST CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC
102 filing(s).
Item | File Stamp | Party | Filing Description |
---|---|---|---|
1 | 8/9/2018 | MC CORD DEVELOPMENT | COMPLAINT OF MCCORD DEVELOPMENT, INC. AGAINST CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC |
2 | 8/14/2018 | PUC OPDM | ORDER NO.1 REQUIRING RESPONSES |
3 | 9/5/2018 | PUC LEGAL | MOTION FOR EXTENSION |
4 | 9/5/2018 | CENTERPOINT ENERGY HOUSTON ELECTRIC , LLC | CenterPoint Energy Houston Electric, LLC`s Response to Complaint |
5 | 9/6/2018 | MCCORD DEVELOPMENT, INC | RESPONSE TO MOTION FOR EXTENSION |
6 | 9/7/2018 | CENTERPOINT ENERGY HOUSTON ELECTRIC , LLC | RESPONSE TO MOTION FOR EXTENSION |
7 | 9/10/2018 | PUC OPDM | ORDER NO.2 GRANTING EXTENSION |
8 | 9/20/2018 | PUC LEGAL | REFERRAL STATEMENT OF POSITION |
9 | 10/8/2018 | PUC OPDM | ORDER OF REFERRAL |
10 | 10/18/2018 | PUC LEGAL | PROPOSED LIST OF ISSUES |
11 | 10/18/2018 | MCCORD DEVELOPMENT, INC. | PROPOSED LIST OF ISSUES |
12 | 10/18/2018 | CENTERPOINT ENERGY HOUSTON ELECTRIC , LLC | PROPOSED LIST OF ISSUES |
13 | 11/1/2018 | PUC OPDM | DRAFT PRELIMINARY ORDER AND MEMO |
14 | 11/8/2018 | PUC OPDM | PRELIMINARY ORDER |
15 | 11/8/2018 | PUC OPDM | OUTGOING COMMISSION SIGNED ORDER MAIL LOG |
16 | 11/12/2018 | PUC LEGAL | 1ST RFI TO MCCORD DEVELOPMENT, INC |
17 | 11/12/2018 | PUC LEGAL | 1ST RFI TO CENTERPOINT |
18 | 11/29/2018 | CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC | CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC’S RESPONSES TO THE PUBLIC UTILITY COMMISSION OF TEXAS’S FIRST SET OF RFIS |
19 | 12/3/2018 | MC CORD DEVELOPMENT | McCord Development, Inc.`s Responses to Commission Staff of the PUC`s 1st RFI |
20 | 12/18/2018 | MCCORD DEVELOPMENT, INC. | 1ST RFI TO CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC |
21 | 12/18/2018 | SOAH | SOAH ORDER NO.1 FILING DESCRIPTION, WAIVER OF INFORMAL RESOLUTION PROCEDURES, NOTICE OF PREHEARING CONFERENCE, AND PROCEDURES |
22 | 1/17/2019 | CENTERPOINT ENERGY HOUSTON ELECTRIC | CenterPoint Energy Houston Electric, LLC Motion for Entry of Protective Order |
23 | 1/22/2019 | CENTERPOINT ENERGY HOUSTON ELECTRIC , LLC | CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC’S RESPONSES TO MCCORD DEVELOPMENT INC.’S FIRST SET OF RFIS |
24 | 1/28/2019 | MCCORD DEVELOPMENT, INC. | 2ND RFI TO CENTERPOINT |
25 | 1/29/2019 | SOAH | SOAH ORDER NO.2 MEMORIALIZING PREHEARING CONFERENCE; ADOPTING PROCEDURAL SCHEDULE; ADOPTING PROTECTIVE ORDER; AND NOTICE OF HEARING |
26 | 1/30/2019 | PUC LEGAL | PROTECTIVE ORDER CERTIFICATIONS |
27 | 1/31/2019 | MCCORD DEVELOPMENT, INC. | McCord Development, Inc.`s Protective Order Certifications |
28 | 1/31/2019 | MCCORD DEVELOPMENT, INC | THIRD RFI TO CENTERPOINT ENERGY HOUSTON ELECTRIC LLC |
29 | 1/31/2019 | CENTERPOINT ENERGY HOUSTON ELECTRIC LLC | NOTICE AND INDEX OF CONFIDENTIAL DOCUMENTS FILED IN ITS RESPONSE TO MCCORD DEVELOPMENT, INC'S FIRST SET OF RFI'S. |
30 | 1/31/2019 | CENTERPOINT ENERGY HOUSTON ELECTRIC LLC | CONFIDENTIAL - ATTACHMENTSTO MCCORD DEVELOPMENT, INC - QUESTION MCCORD01-02; BATE STAMP: 1 - 194 |
31 | 1/31/2019 | CENTERPOINT ENERGY HOUSTON ELECTRIC LLC | CONFIDENTIAL - ATTACHMENTS TO MCCORD DEVELOPMENT, INC - QUESTION MCCORD01-03; BATE STAMP: 1 - 41 |
32 | 1/31/2019 | CENTERPOINT ENERGY HOUSTON ELECTRIC LLC | CONFIDENTIAL - ATTACHMENTS TO MCCORD DEVELOPMENT, INC - QUESTION MCCORD01 - 06; BATE STAMP: 1 - 56 |
33 | 2/1/2019 | MCCORD DEVELOPMENT, INC. | BRIEF ON THRESHOLD ISSUE OF BURDEN OF PROOF |
34 | 2/1/2019 | CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC | CenterPoint`s Brief on Threshold Issue - Burden of Proof |
35 | 2/5/2019 | KENNEDY REPORTING SERVICE | PREHEARING CONFERENCE TUESDAY, JANUARY 15, 2019 PAGES 1-11 |
36 | 2/5/2019 | MCCORD DEVELOPMENT, INC. | 4TH RDI TO CENTERPOINT ENERGY |
37 | 2/7/2019 | MCCORD DEVELOPMENT, INC | PROTECTIVE ORDER CERTIFICATIONS |
38 | 2/7/2019 | CENTERPOINT ENERGY HOUSTON ELECTRIC , LLC | NOTICE AND INDEX OF CONFIDENTIAL DOCUMENTS FILED IN ITS RESPONSE TO MCCORD DEVELOPMENT, INC'S SECOND RFI |
39 | 2/7/2019 | CENTERPOINT ENERGY HOUSTON | CenterPoint Energy Houston Electric, LLCs Responses to McCord Development, Incs Second Set of RFIs |
40 | 2/7/2019 | CENTERPOINT ENERGY HOUSTON | FILED INCORRECTLY- SEE ITEM #42 |
41 | 2/7/2019 | CENTERPOINT ENERGY HOUSTON | CONFIDENTIAL - CEHE'S RESPONSE TO MCCORD SECOND RFI MCCORD 02 - 02 (CONF); BATE STAMP: C-1 TO C-1 |
42 | 2/8/2019 | CENTERPOINT ENERGY HOUSTON ELECTRIC | CONFIDENTIAL-CONFIDENTIAL - CEHE'S RESPONSE TO MCCORD SECOND RFI MCCORD 02 - 01 (CONF); BATE STAMP: C-1 TO C-3 |
43 | 2/12/2019 | MCCORD DEVELOPMENT, INC. | PROTECTIVE ORDER CERTIFICATIONS |
44 | 2/14/2019 | MCCORD DEVELOPMENT, INC. | 5TH RIF TO CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC. |
45 | 2/15/2019 | CENTERPOINT ENERGY HOUSTON ELECTRIC LLC | RESPONSES TO THE MCCORD DEVELOPMENT INC'S FOURTH SET OF RFI'S |
46 | 2/19/2019 | CENTERPOINT ENERGY HOUSTON ELECTRIC | CenterPoint Energy Houston Electric, LLC`s Responses to the McCord Development`s Third Set of RFIs |
47 | 2/19/2019 | CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC | CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC'S REQUEST FOR ORDER REQUIRING COMPLAINANTS TO SPECIFY RELIEF REQUESTED |
48 | 2/19/2019 | CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC | CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC'S OBJECTIONS TO MCCORD DEVELPOMENT, INC.'S 5TH RFI |
49 | 2/22/2019 | MCCORD DEVELOPMENT, INC. | MCCORD DEVELOPMENT, INC.'S 6TH RFI TO CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC. |
50 | 2/25/2019 | CENTERPOINT ENERGY HOUSTON ELECTRIC , LLC | CenterPoint Energy Houston Electric LLCs Responses to the McCord Development Inc`s Fifth Set of RFIs |
51 | 2/25/2019 | CENTERPOINT ENERGY HOUSTON ELECTRIC , LLC | CONFIDENTIAL- CEHE'S RESPONSE TO MCCORD 5TH RFI MCCORD 5-16 (CONF.) BATE STAMP- C-1 TO C-1 |
52 | 2/25/2019 | CENTERPOINT ENERGY HOUSTON ELECTRIC , LLC | CONFIDENTIAL- CEHE'S RESPONSE TO MCCORD 5TH RFI MCCORD 5-20 (CONF.) BATE STAMP- C-1 TO C-5 |
53 | 2/26/2019 | MCCORD DEVELOPMENT, INC. | McCord Development, Inc.`s Motion to Compel Centerpoint to Respond to McCord`s Fifth Set of RFIs |
54 | 2/26/2019 | MCCORD DEVELOPMENT, INC. | LETTER TO JUDGE BAILEY |
55 | 3/1/2019 | CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC | CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC'S NOTIFICATION OF AGREED CHANGE IN DEADLINE |
56 | 3/1/2019 | CENTERPOINT ENERGY HOUSTON ELECTRIC , LLC | CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC'S SUPPLEMENT TO ITS RESPONSES TO COMMISSION STAFF'S 1ST SET OF RFI AND MCCORD DEVELOPMENT, INC'S 1ST THROUGH 4TH SET OF RFI |
57 | 3/1/2019 | MCCORD DEVELOPMENT INC. | FIRST AMENDED COMPLAINT OF MCCORD DEVELOPMENT, INC. |
58 | 3/4/2019 | CENTERPOINT ENERGY HOUSTON ELECTRIC LLC | CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC’S RESPONSES TO THE MCCORD DEVELOPMENT INC.’S SIXTH SET OF RFIS |
59 | 3/4/2019 | CENTERPOINT ENERGY HOUSTON ELECTRIC LLC | NOTICE AND INDEX OF CONFIDENTIAL DOCUMENTS FILED IN ITS RESPONSE TO MCCORD DEVELOPMENT, INC.'S 5TH SET OF RFI |
60 | 3/4/2019 | CENTERPOINT ENERGY HOUSTON ELECTRIC LLC | NOTICE AND INDEX OF CONFIDENTIAL DOCUMENTS FILED IN ITS RESPONSE TO MCCORD DEVELOPMENT, INC.'S 6TH SET OF RFI |
61 | 3/4/2019 | CENTERPOINT ENERGY HOUSTON ELECTRIC LLC | CONFIDENTIAL- RESPONSE TO MCCORD 5TH RFI BATE STAMP 1-13 |
62 | 3/4/2019 | CENTERPOINT ENERGY HOUSTON ELECTRIC LLC | CONFIDENTIAL- RESPONSE TO MCCORD 5TH RFI BATE STAMP 1-1 |
63 | 3/8/2019 | CENTERPOINT ENERGY HOUSTON ELECTRIC , LLC | CenterPoint Energy Houston Electric LLCs Response to McCord Development Incs Motion to Compel Responses to its Fifth Set of Requests for Information |
64 | 3/8/2019 | CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC | AMENDED RESPONSE TO MCCORD DEVELOPMENT, INC.'S 4TH SER OF RFI |
65 | 3/8/2019 | CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC | NOTICE AND INDEX OF CONFIDENTIAL DOCUMENTS FILED IN ITS AMENDED RESPONSE TO MCCORD DEVELOPMENT, INC.'S 5TH SET OF RFI |
66 | 3/8/2019 | CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC | AMENDED RESPONSE TO MCCORD DEVELOPMENT, INC.'S 5TH SET OF RFI |
67 | 3/8/2019 | CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC | CONFIDENTIAL- AMENDED RESPONSE TO MCCORD DEVELOPMENT, INC.'S 5TH SET OF RFI BATE STAMP C-1 - C-1 |
68 | 3/8/2019 | MCCORD DEVELOPMENT INC. | MCCORD DEVELOPMENT, INC.S 7TH RFI TO CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC. |
69 | 3/11/2019 | MCCORD DEVELOPMENT INC. | MCCORD DEVELOPMENT, INC.'S REPLY TO CENTERPOINT REPONSES TO MOTION TO COMPEL |
70 | 3/13/2019 | CENTERPOINT ENERGY HOUSTON ELECTRIC LLC | CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC'S AMENDED RESPONSE TO MCCORD DEVELOPMENT, INC.'S 5TH SET OF RFI SPECIFICALLY RFI 05-17; AND NOTIFICATION OF RESOLUTION OF DISPUTE REGARDING RFI 5-17 |
71 | 3/13/2019 | CENTERPOINT ENERGY HOUSTON ELECTRIC LLC | CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC'S RESPONSE TO MCCORD DEVELOPMENT, INC. AND GENERATION PARK MANAGEMENT DISTRICT'S AMENDED COMPLAINT AND ASSERTION OF AFFIRMATIVE DEFENSES |
72 | 3/18/2019 | CENTERPOINT ENERGY HOUSTON ELECTRIC LLC | NOTICE AND INDEX OF CONFIDENTIAL DOCUMENTS FILIED IN ITS REPONSE TO MCCORD DEVELOPMENT, INC'S 7TH RFI |
73 | 3/18/2019 | CENTERPOINT ENERGY HOUSTON ELECTRIC , LLC | CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC’S RESPONSES TO THE MCCORD DEVELOPMENT INC.’S SEVENTH SET OF RFI’s |
74 | 3/18/2019 | CENTERPOINT ENERGY HOUSTON ELECTRIC , LLC | CONFIDENTIAL- CEHE'S REPONSE TO MCCORD 7TH RFI MCCORD 07-11 (CONF.) BATE STAMP- C-1 TO C-35 |
75 | 3/25/2019 | SOAH | SOAH ORDER NO. 3 RULING ON MOTION TO COMPEL |
76 | 3/25/2019 | MCCORD DEVELOPMENT INC. | 8TH RFI TO CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC |
77 | 3/27/2019 | CENTERPOINT ENERGY HOUSTON ELECTRIC LLC | CenterPoint Energy Houston Electric LLC`s Third Amended Response to McCord Development Inc`s Fifth Set of Requests for Information |
78 | 4/2/2019 | PUC LEGAL | NOTICE OF CHANGE OF COUNSEL |
79 | 4/4/2019 | CENTERPOINT ENERGY HOUSTON ELECTRIC , LLC | CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC RESPONSES TO THE MCCORD DEVELOPMENT INC. EIGHT SET OF RFIS |
80 | 4/5/2019 | MCCORD DEVELOPMENT, INC. | Direct Testimony and Exhibits of Bryan Ruth |
81 | 4/5/2019 | MCCORD DEVELOPMENT, INC. | Direct Testimony and Exhibits of Kevin J. Mara |
82 | 4/5/2019 | MCCORD DEVELOPMENT, INC. | CONFIDENTIAL- PORTION TO THE DIRECT TESTIMONY AND EXHIBITS OF BRYAN RUTH BATE STAMP- 1 TO 171 AND CD |
83 | 4/5/2019 | MCCORD DEVELOPMENT, INC. | CONFIDENTIAL- PORTION TO THE DIRECT TESTIMONY AND EXHIBITS OF KEVIN MARA BATE STAMP- 1 TO 4 |
84 | 4/5/2019 | MCCORD DEVELOPMENT, INC. | Public Workpapers to the Direct Testimony of Kevin J. Mara |
85 | 4/5/2019 | MCCORD DEVELOPMENT, INC. | CONFIDENTIAL- WORKPAPERS TO THE DISTRICT TESTIMONY AND EXHIBITS OF KEVIN J. MARA P.E BATE STAMP- CD |
86 | 5/3/2019 | SOAH | SOAH ORDER NO.4- RULING ON BUSSINESS OF PERSUASION AND PRODUCTION OF EVIDENCE |
87 | 6/6/2019 | CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC | UNOPPOSED MOTION TO ABATE PROCEDURAL SCHEDULE |
88 | 6/7/2019 | SOAH | SOAH ORDER NO.5- ABATING PROCEDURAL SCHEDULE, CANCELING HEARING, AND REQUESTING STATUS REPORTS |
89 | 7/1/2019 | CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC | JOINT STATUS REPORT |
90 | 7/26/2019 | CENTERPOINT ENERGY HOUSTON ELECTRIC | JOINT STATUS REPORT |
91 | 7/31/2019 | MCCORD DEVELOPMENT INC. | 2ND AMENDED COMPLIANT OF MCCORD DEVELOPMENT INC. AND GENERATION PARK MANAGEMENT DISTRICT |
92 | 8/16/2019 | CENTERPOINT ENERGY HOUSTON ELECTRIC , LLC | JOINT STATUS REPORT |
93 | 8/21/2019 | CENTERPOINT ENERGY HOUSTON ELECTRIC | RESPONSE TO THE SECOND AMENDED COMPLAINT OF MCCORD DEVELOPMENT, INC. AND GENERATION PARK MANAGEMENT DISTRICT |
94 | 8/29/2019 | SOAH | SOAH ORDER NO.6 REQUESTING REVISED PROCEDURAL SCHEDULE |
95 | 9/11/2019 | MCCORD DEVELOPMENT INC. | RESPONSE TO SOAH ORDER NO.6 |
96 | 9/19/2019 | MCCORD DEVELOPMENT, INC., GENERATION PARK MANAGEMENT DISTRICT AND CENTERPOINT ENERGY HOUSTON ELECTRIC | JOINT REQUEST FOR EXTENSION OF TIME TO FILE PROCEDURAL SCHEDULE |
97 | 9/20/2019 | SOAH | SOAH ORDER NO.7- GRANTING JOINT REQUEST FOR EXTENSION OF TIME TO FIILE PROCEDUREAL SCHEDULE |
98 | 9/27/2019 | CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC | JOINT MOTION TO ABATE PROCEDURAL SCHEDULE |
99 | 9/30/2019 | SOAH | SOAH ORDER NO.8- GRANTING JOINT MOTION TO ABATE PROCEDURAL SCHEDULE |
100 | 10/17/2019 | MCCORD DEVELOPMENT, INC., GENERATION PARK MANAGEMENT DISTRICT AND CENTERPOINT ENERGY HOUSTON ELECTRIC | MOTION TO WITHDRAW AND REQUEST FOR DISMISSAL |
101 | 10/17/2019 | SOAH | SOAH ORDR NO.9- GRANTING MOTION WITHDRAW AND DISSMISSING CASE |
102 | 11/4/2019 | PUC LEGAL | NOTICE OF CHANGE OF COUNSEL |