Filings for 48334



Case Style   APPLICATION OF SOUTHWESERN ELECTRIC POWER COMPANY TO ADJUST ITS ENERGY EFFICIENCY COST RECOVERY FACTOR AND RELATED RELIEF

43 filing(s).

Item File Stamp Party Filing Description
1 5/1/2018 SOUTHWESTERN ELECTRIC POWER COMPANY APPLICATION OF SOUTHWESERN ELECTRIC POWER COMPANY TO ADJUST ITS ENERGY EFFICIENCY COST RECOVERY FACTOR AND RELATED RELIEF
2 5/1/2018 SWEPCO CONFIDENTIAL- SCHEDULE J BATE STAMP 1-101
3 5/2/2018 PUC OPDM ORDER OF REFERRAL
4 5/3/2018 SWEPCO PROOF OF NOTICE
5 5/4/2018 SOAH ORDER NO.1 DESCRIBING CASE, SETTING DEADLINES, DISCUSSING PROCEDURES, AND APPROVING PROTECTIVE ORDER
6 5/10/2018 PUC OPDM ORDER REVISING DEADLINE TO FILE LISTS OF ISSUES
7 5/15/2018 PUC LEGAL 1ST RFI TO SWEPCO
8 5/18/2018 SOUTHWESTERN ELECTRIC POWER COMPANY SWEPCO LIST OF ISSUES
9 5/18/2018 PUC OPDM DRAFT PRELIMINARY ORDER
10 5/18/2018 PUC LEGAL COMMISSION STAFF'S LIST OF ISSUES
11 5/25/2018 PUC OPDM PRELIMINARY ORDER
12 5/25/2018 PUC OPDM OUTGOING COMMISSION-SIGNED ORDER MAIL LOG
13 5/31/2018 PUC LEGAL 2ND RFI TO SWEPCO
14 5/31/2018 PUC LEGAL CONFIDENTIAL- 2ND RFI TO SWEPCO BATE STAMP 1-1
15 6/4/2018 SOUTHWESTERN ELECTRIC POWER COMPANY SWEPCO`S RESPONSE TO STAFF`S 1ST RFI
16 6/12/2018 PUC LEGAL RECOMMENDATION ON SUFFICIENCY OF APPLICATION AND NOTICE
17 6/12/2018 SWEPCO JOINT PROPOSED SCHEDULE
18 6/14/2018 SPS RESPONSE TO COMMISSION STAFF'S 2ND RFI
19 6/14/2018 SPS CONFIDENTIAL- RESPONSE TO STAFF'S 2ND, QUESTION NO STAFF 2-3 BATE STAMP 1-1
20 6/14/2018 PUC LEGAL request for a hearing and amended procedural schedule
21 6/13/2018 SOAH SOAH ORDER NO. 3 ADOPTING PROCEDURAL SCHEDULE; NOTICE OF HEARING ON THE MERITS
22 6/21/2018 PUC LEGAL COMMISSION STAFF'S REDACTED THIRD RFI TO SOUTHWESTERN ELECTRIC POWER COMPANY QUESTION NO. STAFF 3 - 1
23 6/21/2018 PUC LEGAL CONFIDENTIAL - COMMISSION STAFF'S CONFIDENTIAL SECOND RFI TO SOUTHWESTERN ELECTRIC POWER COMPANY QUESTION NO. STAFF 3 - 1; BATE STAMP: 1
24 6/28/2018 PUC LEGAL 4TH RFI TO SWEPCO
25 6/29/2018 SOUTHWESTERN ELECTRIC POWER COMPANY SOUTHWESTERN ELECTRIC POWER COMPANY’S AMENDED APPLICATION
26 7/11/2018 SOUTHWESTERN PUBLIC SERVICE COMPANY RESPONSE TO COMMISSION STAFF'S FIRST RFI
27 7/18/2018 SWEPCO RESPONSE TO COMMISSION STAFF'S 4TH RFI
28 7/18/2018 SWEPCO CONFIDENTIAL- RESPONSE TO COMMISSION STAFF'S 4TH RFI BATE STAMP 1-85
29 7/27/2018 SWEPCO LETTER TO JUDGE ARNOLD
30 8/9/2018 SWEPCO REQUEST FOR EXTENSION
31 8/15/2018 SOUTHWESTERN ELECTRIC POWER COMPANY Stipulation
32 8/15/2018 SWEPCO JOINT MOTION TO ADMIT EVIDENCE AND REMAND TO THE PUBLIC UTILITY COMMISSION OF TEXAS
33 8/15/2018 PUC INFRASTRUCTURE & RELIABILITY AFFIDAVIT OF ALICIA MALOY
34 8/15/2018 PUC INFRASTRUCTURE & RELIABILITY AFFIDAVIT OF NANCY PALMA
35 8/15/2018 PUC RATE REGULATION AFFIDAVIT OF GLENDA SPENCE
36 8/17/2018 SOAH SOAH ORDER NO.4 ADMITTING EVIDENCE, REMANDING CASE TO COMMISSION, AND DISMISING DOCKET
37 10/5/2018 PUC OPDM Proposed Order
38 10/5/2018 SOAH SOAH ORDER NO.2 FINDING APPLICATION ADMINISTRATIVELY SUFFICIENT AND APPROVING NOTICE
39 10/9/2018 PUC LEGAL CORRECTIONS TO THE PROPOSED ORDER
40 10/10/2018 PUC OPDM PROPOSED ORDER MEMO
41 10/12/2018 PUC OPDM ORDER
42 10/12/2018 PUC OPDM OUTGOING COMMISSION SIGNED ORDER MAIL LOG
43 10/17/2018 SWEPCO CLEAN COPY OF EECRF
Export to Excel