Filings for 47174



Case Style   APPLICATION OF LIBERTY UTILITIES (TALL TIMBERS SEWER) CORP. TO AMEND A SEWER CERTIFICATE OF CONVENIENCE AND NECESSITY IN SMITH COUNTY (ACADIA PLACE)

47 filing(s).

Item File Stamp Party Filing Description
1 5/16/2017 LIBERTY UTILITIES (TALL TIMBERS SEWER) CORP APPLICATION OF LIBERTY UTILITIES (TALL TIMBERS SEWER) CORP. TO AMEND A SEWER CERTIFICATE OF CONVENIENCE AND NECESSITY IN SMITH COUNTY (ACADIA PLACE)
2 5/19/2017 PUC CADM ORDER NO. 1 REQUIRING COMMENTS ON ADMINISTRATIVE COMPLETENESS AND NOTICE; REQUESTING PROCEDURAL SCHEDULE, AND ADDRESSING OHER PROCEDURAL MATTERS
3 5/19/2017 PUC CADM NOTICE OF APPLICATION TO AMEND A SEWER CCN
4 5/22/2017 PUC CADM ACKNOWLEDGMENT OF RECEIPT
5 6/12/2017 PUC LEGAL COMMISSION STAFF'S FIRST RFI TO LIBERTY UTILITIES (TALL TIMBERS SEWER) CORP. QUESTION NOS. STAFF 1-1 THROUGH STAFF 1-2
6 6/16/2017 PUC LEGAL COMMISSION STAFF'S FIRST ADMINISTRATIVE COMPLETENESS RECOMMENDATION
7 6/20/2017 PUC CADM ORDER NO. 2 FINDING APPLICATION INCOMPLETE AND DEFICIENT, ESTABLISHING DEADLINES AND OPPORTUNITY TO CURE
8 6/21/2017 PUC CADM FILED IN ERROR, SEE DOCKET No. 47274, ITEM 6 - ACKNOWLEDGEMENT OF RECEIPT
9 6/27/2017 LIBERTY (TALL TIMBERS SEWER) CORP. RESPONSE TO STAFF'S FIRST ADMINISTRATIVE COMPLETENESS RECOMMENDATION
10 7/3/2017 LIBERTY (TALL TIMBERS SEWER) CORP. RESPONSE TO COMMISSION STAFF'S FIRST RFI
11 8/4/2017 PUC LEGAL COMMISSION STAFF'S SECOND RFI TO LIBERTY UTILITIES (TALL TIMBERS SEWER) CORP. QUESTION NOS. STAFF 2 - 1
12 8/17/2017 PUC LEGAL Commission Staff`s Supplemental Recommendation on Administrative Completeness
13 8/18/2017 PUC CADM ORDER NO. 3 DEEMING APPLICATION ADMINISTRATIVELY COMPLETE, ADDRESSING NOTICE; AND ESTABLISHING PROCEDURAL SCHEDULE
14 8/24/2017 LIBERTY UTILITIES (TALL TIMBERS SEWER) CORP REQUEST FOR EXTENSION TO FILE RESPONSE TO REQUEST FOR INFORMATION
15 8/30/2017 PUC CADM ORDER NO. 4 EXTENDING DEADLINE
16 8/31/2017 LIBERTY UTILITIES (TALL TIMBERS SEWER) CORPORATION Responses to Commission Staff`s Second Request for Information
17 9/26/2017 PUC LEGAL COMMISSION STAFF'S THIRD RFI TO LIBERTY UTILITIES (TALL TIMBERS SEWER) CORP. QUESTION NO. STAF 3-1
18 10/9/2017 PUC LEGAL COMMISSION STAFF'S RECOMMENDATION ON SUFFICIENCY OF NOTICE
19 10/12/2017 PUC CADM ORDER NO. 5 ADDRESSING NOTICE DEFICIENCY, ESTABLISHING DEADLINES
20 12/4/2017 PUC LEGAL COMMISSION STAFF'S SUPPLEMENTAL RECOMMENDATION ON SUFFICIENCY OF NOTICE
21 12/7/2017 PUC CADM ORDER NO. 6 NOTICE REMAINS DEFICIENT, EXTENDING DEADLINES
22 12/11/2017 LIBERTY (TALL TIMBERS SEWER) CORP. PUBLISHER'S AFFIDAVIT
23 1/3/2018 LIBERTY UTILITIES ( TALL TIMBERS) CORP. AFFIDAVIT OF NOTICE TO NEIGHBORING UTILITIES, LANDOWNERS AND CITIES
24 1/11/2018 PUC LEGAL COMMISSION STAFF'S SECOND SUPPLEMENTAL RECOMMENDATION ON SUFFICIENCY OF NOTICE
25 1/19/2018 PUC CADM ORDER NO. 7 NOTICE REMAINS DEFICIENT; ESTALBISHING DEADLINES FOR OPPORTUNITY TO CURE DEFICIENCIES
26 2/6/2018 LIBERTY UTILITIES (TALL TIMBERS SEWER) CORP AFFIDAVIT OF NOTICE TO NEIGHBORING UTILITIES AMD LANDOWNERS AND CITIES
27 2/6/2018 LIBERTY UTILITIES ( TALL TIMBERS) CORP. AFFIDAVIT OF NOTICE TO NEIGHBORING UTILITIES AMD LANDOWNERS AND CITIES
28 2/8/2018 PUC LEGAL COMMISSION STAFF'S 3RD SUPPLEMENTAL RECOMMENDATION OF SUFFICIENCY OF NOTICE
29 2/13/2018 PUC CADM ORDER NO.8 FINDING NOTICE SUFFICIENT AND ADOPTING PROCEDURAL SCHEDULE
30 3/14/2018 LIBERTY UTILITIES RESPONSE TO COMMISSION STAFF'S 3RD RFI
31 3/27/2018 PUC LEGAL COMMISSION STAFF'S 4TH RFI TO LIBERTY UTILITIES
32 5/1/2018 PUC LEGAL COMMISSION STAFF'S MOTION TO COMPEL
33 5/1/2018 PUC LEGAL NOTICE OF CHANGE OF COUNSEL
34 5/11/2018 PUC OPDM ORDER NO.9 GRANTING MOTION TO COMPEL; SUSPENDING PROCEDURAL SCHEDULE
35 5/16/2018 LIBERTY UTILITIES (TALL TIMBERS SEWER) CORPORATION Liberty Utilities Response to Staff`s 4th RFI
36 5/17/2018 PUC LEGAL NOTICE OF CHANGE OF COUNSEL
37 5/18/2018 PUC LEGAL COMMISSION STAFF'S PROPOSED SCHEDULE IN RESPONSE TO ORDER NO. 9
38 5/21/2018 PUC OPDM ORDER NO.10 ADOPTING PROCEDURAL SCHEDULE
39 7/19/2018 LIBERTY UTILITIES (W00DMARK) CORP. CONSENT FORM
40 7/19/2018 PUC LEGAL Commission Staff`s Final Recommendation
41 8/23/2018 PUC LEGAL JOINT PROPOSED NOTICE OF APPROVAL AND MOTION TO ADMIT EVIDENCE
42 11/13/2018 PUC OPDM ORDER NO.11 ADMITTING EVIDENCE
43 12/6/2018 PUC LEGAL NOTICE OF CHANGE OF COUNSEL
44 3/21/2019 PUC OPDM ORDER NO. 13- REQURING ELECTRONIC FILINGS
45 3/21/2019 SOAH (moved to correct dkt. 48583)SOAH ORDER NO.3- RULING ON MOTION TO COMPEL
46 3/22/2019 PUC OPDM NOTICE OF APPROVAL
47 3/22/2019 PUC OPDM OUTGOING COMMISSION-SIGNED MAIL LOG
Export to Excel