Filings for 37574
Case Style JOINT APPLICATION OF AEP TEXAS CENTRAL COMPANY AND ELECTRIC TRANSMISSION TEXAS, LLC TO TRANSFER CERTIFICATE RIGHTS AND FOR APPROVAL OF TRANSFER OF FACILITIES IN NUECES COUNTY, TEXAS
34 filing(s).
Item | File Stamp | Party | Item Type | Filing Description |
---|---|---|---|---|
1 | 10/16/2009 | AEP TEXAS CENTRAL COMPANY | PL | JOINT APPLICATION OF AEP TEXAS CENTRAL COMPANY AND ELECTRIC TRANSMISSION TEXAS, LLC TO TRANSFER CERTIFICATE RIGHTS AND FOR APPROVAL OF TRANSFER OF FACILITIES IN NUECES COUNTY, TEXAS |
2 | 10/16/2009 | AEP TEXAS CENTRAL COMPANY | CONF | CONFIDENTIAL - SERVICES AGREEMENT, BATE STAMP 1-73 |
3 | 10/19/2009 | PUC CADM | PL | ORDER NO.1: REQUIRING COMMENTS ON SUFFICIENCY OF APPLICATION AND NOTICE; REQUIRING AGREED PROPOSED PROCEDURAL SCHEDULE AND ENTERING PROTECTIVE ORDER |
4 | 10/23/2009 | SOUTH TEXAS AGGREGATION PROJECT, INC. | PL | MOTION TO INTERVENE |
5 | 10/29/2009 | SOUTH TEXAS AGGREGATION PROJECT, INC. | RFI | 1ST RFI TO AEP TCC & ETT |
6 | 11/2/2009 | PUC CADM | PL | ORDER NO. 2 GRANTING SOUTH TEXAS AGGREGATION PROJECT'S MOTION TO INTERVENE |
7 | 11/9/2009 | AEP TEXAS CENTRAL AND NORTH COMPANIES, ET AL | RFI | AEP TCC & ETT Response to STAP's 1st RFI |
8 | 11/10/2009 | PUC LEGAL | PL | STAFF'S RESPONSE TO ORDER NO.1 |
9 | 11/10/2009 | AEP ET AL | PL | JOINT PROPOSED PROCEDURAL SCHEDULE |
10 | 11/12/2009 | PUC CADM | PL | ORDER NO.3: DEEMING APPLICATION AND NOTICE SUFFICIENT; AND SETTTING PROCEDURAL SCHEDULE |
11 | 11/13/2009 | SOUTH TEXAS AGGREGATION PROJECT | RFI | 2ND RFI TO AEP TCC, AEP TNC, AND ETT |
12 | 11/16/2009 | AEP TEXAS CENTRAL CO | PL | PROOF OF NOTICE |
13 | 11/19/2009 | PUC LEGAL | RFI | STAFF'S 1ST RFI TO ELECTRIC TRANSMISSION TEXAS, LLC'S #RS1-5 |
14 | 11/19/2009 | PUC LEGAL | RFI | STAFF'S 1ST RFI TO AEP TCC #RS 1-7 |
15 | 11/23/2009 | PUC LEGAL | RFI | STAFF'S 2ND RFI TO AEP TCC #NF 1-3 |
16 | 11/23/2009 | PUC LEGAL | RFI | STAFF'S 2ND RFI TO ELECTRIC TRANSMISSION TEXAS, LLC'S #NF 1-3 |
17 | 11/23/2009 | AEP TCC & ELECTRIC TRANSMISSION TEXAS, LLC | RFI | RESPONSE TO SOUTH TEXAS AGGREGRATION PROJECTS 2ND RFI |
18 | 11/23/2009 | AEP TCC & ELECTRIC TRANSMISSION TEXAS, LLC | PL | OBJECTIONS TO SOUTH TEXAS AGGREGATION PROJECT'S 2ND RFI |
19 | 11/24/2009 | AEP TEXAS | PL | AGREED MOTION TO MODIFY PROCEDURAL SCHEDULE |
20 | 11/25/2009 | AEP TCC | RFI | Response to Staff's 1st RFI |
21 | 11/25/2009 | AEP TEXAS AND ELECTRIC TRANSMISSION TEXAS, LLC | RFI | RESPONSE TO COMMISSION STAFF'S 1ST RFI |
22 | 11/25/2009 | PUC CADM | PL | ORDER NO. 4: GRANTING MOTION TO MODIFY PROCEDURAL SCHEDULE |
23 | 12/2/2009 | SOUTH TEXAS AGGREGATION PROJECT | PL | MOTION TO COMPEL RESPONSES TO IT'S 2ND SET OF RFI TO AEP TCC AND ETT |
24 | 12/3/2009 | AEP TCC | RFI | RESPONSE TO STAFF'S 2ND RFI |
25 | 12/3/2009 | ELECTRIC TRANSMISSION TEXAS, LLC | RFI | RESPONSE TO STAFF'S 2ND RFI |
26 | 12/4/2009 | SOUTH TEXAS AGGREGATION PROJECT, INC. | PL | WITHDRAWAL OF MOTION TO COMPEL |
27 | 12/7/2009 | ETT | RFI | ETT's Supplemental Response to STAP's 2nd RFI, Questions 1 & 2 |
28 | 12/14/2009 | PUC LEGAL | PL | Staff's Final Recommendation |
29 | 12/30/2009 | PUC LEGAL | PL | PROPOSED ORDER |
30 | 1/6/2010 | PUC CADM | PL | PROPOSED ORDER |
31 | 1/19/2010 | AEP TEXAS CENTRAL COMPANY | PL | LETTER STATING NO CORRECTIONS OR EXCEPTIONS TO PROPOSED ORDER DATED JANUARY 6, 2010 |
32 | 1/29/2010 | PUC CADM | PL | Order |
33 | 2/2/2010 | PUC CADM | PL | OUTGOING COMMISSION SIGNED ORDER MAIL LOG |
34 | 8/18/2011 | ELECTRIC TRANSMISSION TEXAS LLC | PL | FINAL TRANSFER JOURNAL ENTRIES |