Filings for 30365
Case Style APPLICATION OF BRAZOS ELECTRIC POWER COOPERATIVE, INC FOR A CERTIFICATE OF CONVENIENCE AND NECESSITY(CCN) FOR A 138-KV DOUBLE CIRCUIT TRANSMISSION LINE AND SUBSTATION IN JOHNSON COUNTY, TEXAS
64 filing(s).
Item | File Stamp | Party | Item Type | Filing Description |
---|---|---|---|---|
1 | 10/27/2004 | BRAZOS ELECTRIC POWER COOPERATIVE, INC. | PL | APPLICATION OF BRAZOS ELECTRIC POWER COOPERATIVE, INC FOR A CERTIFICATE OF CONVENIENCE AND NECESSITY(CCN) FOR A 138-KV DOUBLE CI |
2 | 11/8/2004 | BRAZOS ELECTRIC COOPERATIVE, INC. | PL | Application - Jessica Transmission Project CCN |
3 | 11/10/2004 | PUC POLICY DEVELOPMENT DIVISION | PL | ORDER NO. 1 REQUIRING INFORMATION FROM APPLICANT AND RECOMMENDATION FROM STAFF SUFFICIENCY OF APPLICATION AND NOTICE; ADDRESSING OTHER PROCEDURAL MATTERS |
4 | 11/10/2004 | PUC POLICY DEVELOPMENT DIVISION | PL | NOTICE OF APPLICATION FOR CERTIFICATE OF CONVENIENCE AND NECESSITY FOR A PROPOSED TRANSMISSION LINE IN JOHNSON COUNTY, TEXAS |
5 | 11/10/2004 | PUC POLICY DEVELOPMENT DIVISION | PL | ACKNOWLEDGEMENT OF RECEIPT - NOTICE OF APPLICATION FOR A CERTIFICATE OF CONVENIENCE AND NECESSITY FOR A PROPOSED TRANMISSION LINE IN JOHNSON COUNTY, TEXAS - FILE NAME: 1109C.052 |
6 | 11/16/2004 | PEGGY CAMPOS | PC | COMMENTS |
7 | 11/19/2004 | LA CLEDA PRATER | PC | COMMENTS |
8 | 11/19/2004 | ERNEST PRATER | PC | COMMENTS |
9 | 11/23/2004 | JOHN SMALE | PL | REQUEST TO INTERVENE |
10 | 11/23/2004 | CAROLE CHRISTOPHER | PC | COMMENTS |
11 | 11/24/2004 | BRAZOS ELECTRIC COOPERATIVE, INC. | PL | FIRST RESPONSE TO ORDER NO. 1 |
12 | 12/2/2004 | GERALDINE MCADA | PC | COMMENTS |
13 | 12/2/2004 | JOHN J. BROWN | PC | COMMENTS |
14 | 12/2/2004 | WENDY L. BROWN | PC | COMMENTS |
15 | 12/2/2004 | SANDRA K. BROWN | PC | COMMENTS |
16 | 12/2/2004 | JOHN P. BROWN | PC | COMMENTS |
17 | 12/3/2004 | SAM BRINDLEY | PC | COMMENTS |
18 | 12/3/2004 | BRAZOS ELECTRIC POWER COOPERATIVE, INC. | PL | Brazos Electric's Second Response to Order No. 1 |
19 | 12/8/2004 | PUC POLICY DEVELOPMENT | PL | ORDER NO. 2: GRANTING MOTION TO INTERVENE |
20 | 12/9/2004 | JOHN SMALE | PL | REQUEST TO INTERVENE |
21 | 12/13/2004 | SHAWN PETROWSKY | PC | COMMENTS |
22 | 12/13/2004 | CATHERINE PEATROWSKI | PC | COMMENTS |
23 | 12/13/2004 | PUC LEGAL & ENFORCEMENT | PL | RESPONSE TO ORDER NO. 1 AS TO DEFICIENCIES, NOTICE AND DEADLINE FOR INTERVENTION |
24 | 12/14/2004 | SCOTT BROWN | PC | COMMENTS |
25 | 12/14/2004 | DESTINY BROWN | PC | COMMENTS |
26 | 12/14/2004 | SANDRA HOWSE-GEEO | PC | COMMENTS |
27 | 12/14/2004 | MARIE ZACHRY | PC | COMMENTS |
28 | 12/14/2004 | DONALD GEEO | PC | COMMENTS |
29 | 12/15/2004 | DON ALLISON | PC | COMMENTS |
30 | 12/15/2004 | BRAZOS ELECTRIC POWER COOPERATIVE, INC. | PL | REPLY TO COMMISSION STAFF'S RESPONSE TO ORDER NO. 1 AS TO DEFICIENCIES, NOTICE AND DEADLINE FOR INTERVENTION |
31 | 12/17/2004 | PUC POLICY DEVELOPMENT DIVISION | PL | ORDER NO. 3: ADDRESSING SUFFICIENCY OF APPLICATION AND NOTICE, SUSPENDING DEADLINES AND REQUIRING NEW PROCEDURAL SCHEDULE |
32 | 12/20/2004 | CLAYTON BARNARD | PC | COMMENTS |
33 | 12/21/2004 | JAMES PRATER | PC | COMMENTS |
34 | 12/21/2004 | DON HAGAR | PC | COMMENTS |
35 | 12/21/2004 | STEVE & CATHY SCOTT | PC | COMMENTS |
36 | 12/21/2004 | KATHY PRATER | PC | COMMENTS |
37 | 12/23/2004 | MICHAEL BROWN | PC | COMMENTS |
38 | 1/6/2005 | BRAZOS ELECTRIC POWER COOPERATIVE, INC. | PL | AFFIDAVIT OF DAVID E. MCDANIEL; ERRATA TO UTILITY MUNICIPALITY AND COUNTY GOVERNMENT NOTIFICATION LIST; AND ERRATA TO THE AFFIDAVIT OF DAVID E. MCDANIEL |
39 | 1/6/2005 | PUC LEGAL & ENFORCEMENT | PL | RESPONSE TO ORDER NO. 3 |
40 | 1/13/2005 | PUC POLICY DEVELOPMENT | PL | ORDER NO. 4: ADDRESSING SUFFICIENCY OF NOTICE, REINSTATING DEADLINES AND ESTABLISHING PROCEDURAL SCHEDULE |
41 | 1/25/2005 | PUC LEGAL & ENFORCEMENT | RFI | 1ST SET OF RFI TO BRAZOOS ELECTRIC POWER COOP, INC. |
42 | 2/1/2005 | JOHN SMALE | PL | LETTER TO CONFIRM THAT SMALE HAS ENTERED INTO A ROUTING AGREEMENT WITH BRAZOS ELECTRIC POWER COOP, INC. AND REQUEST TO WITHDRAW HIS INTERVENTION |
43 | 2/1/2005 | BRAZOS ELECTRIC POWER COOPERATIVE, INC. | PL | ROUTING ALIGNMENT AGREEMENT WITH LANDOWNER AND SOLE INTERVENOR |
44 | 2/10/2005 | BRAZOS ELECTRIC POWER COOPERATIVE, INC. | RFI | Brazos Electric's Response to Staff's 1st RFIs |
45 | 2/16/2005 | PUC LEGAL | RFI | STAFF'S SECOND SET OF REQUESTS FOR INFORMATION TO BRAZOS ELECTRIC POWER COOPERATIVE, INC. (AB 2-1 TO AB 2-9) |
46 | 2/18/2005 | PUC LEGAL & ENFORCEMENT | RFI | 3RD SET OF RFI TO BRAZOS ELECTRIC POWER COOP., INC. (AB 3-1 TO AB 3-12) |
47 | 2/28/2005 | PUC POLICY DEVELOPMENT DIVISION | PL | REQUEST FOR EXTENSION OF DEADLINE TO REFER THE DOCKET TO SOAH OR FILE ITS FINAL RECOMMENDATION |
48 | 3/2/2005 | PUC LEGAL | PL | STAFF'S FOURTH SET OF RFI TO BRAZOS ELECTRIC POWER COOPERATIVE, INC. (AB4-1 TO AB 4-9) |
49 | 3/2/2005 | PUC POLICY DEVELOPMENT | PL | ORDER NO.5 GRANTING STAFF'S REQUEST FOR EXTENSION OF DEADLINE |
50 | 3/4/2005 | BRAZOS ELECTRIC POWER COOPERATIVE, INC. | RFI | BEPC Responses to Staff's 3rd RFIs |
51 | 3/4/2005 | BRAZOS ELECTRIC POWER COOPERATIVE, INC. | PL | BEPC Responses to Staff's 2nd RFIs- DISKS INCLUDED |
52 | 3/11/2005 | BRAZOS ELECTRIC POWER COOPERATIVE, INC. | RFI | Brazos Electric's Response to Staff's 4th RFIs |
53 | 3/24/2005 | PUC LEGAL & ENFORCEMENT | PL | COMMISSION STAFF'S FINAL RECOMMENDATION |
54 | 3/30/2005 | BRAZOS ELECTRIC POWER COOPERATIVE, INC. | PL | REQUEST FOR EXTENSION OF MARCH 31, 2005 DEADLINE |
55 | 3/30/2005 | PUC LEGAL & ENFORCEMENT | PL | SUPPLEMENTAL RECOMMENDATION |
56 | 4/4/2005 | PUC POLICY DEVELOPMENT DIVISION | PL | ORDER NO. 6 GRANTING REQUEST TO WITHDRAW INTERVENTION AND REQUEST FOR EXTENSION OF DEADLINE |
57 | 4/7/2005 | BRAZOS ELECTRIC POWER COOPERATIVE, INC. | PL | Joint Proposed Order |
58 | 4/14/2005 | PUC LEGAL | PL | STAFF'S RESPONSE TO JOINT PROPOSED ORDER |
59 | 4/14/2005 | PDD | PL | NOTICE OF APPROVAL |
60 | 4/28/2005 | PUC POLICY DIVISION | PL | ORDER NO. 7 : REQUEST FOR COMMISSION STAFF TO RESPOND TO NOTICE OF APPROVAL |
61 | 5/10/2005 | PUC LEGAL AND ENFORCEMENT DIVISION | PL | RESPONSE TO ORDER NO. 7 |
62 | 5/12/2005 | PUC-POLICY AND DEVELOPMENT | PL | AMENDED NOTICE OF APPROVAL |
63 | 9/6/2005 | JOHN SMALL | PL | REQUEST TO INTERVENE |
64 | 2/11/2019 | CENTRAL RECORDS | PL | SENT OFFSITE TO THE STATE RECORDS CENTER 02/2019 |
Export to Excel |