Filings for 27179
Case Style APPLICATION OF ONCOR ELECTRIC DELIVERY COMPANY FOR A CERTIFICATE OF CONVENIENCE AND NECESSITY (CCN) FOR A PROPOSED TRANSMISSION LINE IN BELL AND CORYELL COUNTIES
179 filing(s).
Item | File Stamp | Party | Item Type | Filing Description |
---|---|---|---|---|
1 | 12/31/2002 | ONCOR ELECTRIC DELIVERY COMPANY | PL | APPLICATION OF ONCOR ELECTRIC DELIVERY COMPANY FOR A CERTIFICATE OF CONVENIENCE AND NECESSITY (CCN) FOR A PROPOSED TRANSMISSION LINE IN BELL AND CORYELL COUNTIES |
2 | 1/6/2003 | PUC POLICY DEVELOPMENT | PL | ORDER NO. 1: REQUIRING RECOMMENDATION ON SUFFIENCY OF APPLICATION AND NOTICE; ADDRESSING OTHER PROCEDURAL MATTERS |
3 | 1/7/2003 | CENTRAL RECORDS | PL | VOID: FILED IN ERROR, SEE DCOKET # 27173, ITEM # 4 |
4 | 1/7/2003 | CENTRAL RECORDS | PL | VOID: FILED IN ERROR, SEE DCOKET # 27173, ITEM # 5 |
5 | 1/8/2003 | PUC POLICY DEVELOPMENT DIVISION | PL | ACKNOWLEDGEMENT OF RECEIPT; NOTICE OF APPLICATION FOR CCN; FILE NAME - 0106b.52 |
6 | 1/8/2003 | PUC POLICY DEVELOPMENT DIVISION | PL | NOTICE OF APPLICATION FOR CCN |
7 | 1/13/2003 | RICARDO WELSH | PL | LETTER OF OPPOSITION |
8 | 1/23/2003 | PUC POLICY DEVELOPMENT DIVISION | PL | INFORMATIONAL NOTICE TO ALL PARTIES OF RECORD RE: WAYS IN WHICH TO PARTICIPATE IN A DOCKET |
9 | 1/24/2003 | ONCOR ELECTRIC DELIVERY COMPANY | PL | RESPONSE TO ORDER NO. 1 REQUIRING RECOMMENDATION ON SUFFICIENCY OF APPLICATION AND NOTICE; ADDRESSING PROCEDURAL MATTERS |
10 | 1/24/2003 | ONCOR ELECTRIC DELIVERY COMPANY | PL | AFFIDAVIT ATTESTING TO THE PROVISION OF NOTICE |
11 | 1/29/2003 | JOHN W. JACKSON | PC | REQUEST TO PARTICIPATE |
12 | 1/31/2003 | CENTRAL RECORDS | PC | VOID, SEE DOCKET NO. 27173, ITEM NO. 16 |
13 | 1/31/2003 | CENTRAL RECORDS | PC | VOID, SEE DOCKET NO. 27173, ITEM NO. 17 |
14 | 1/31/2003 | CENTRAL RECORDS | PC | VOID, SEE DOCKET NO. 27173, ITEM NO. 18 |
15 | 1/31/2003 | CENTRAL RECORDS | PC | VOID, SEE DOCKET NO. 27173, ITEM NO. 19 |
16 | 1/31/2003 | CENTRAL RECORDS | PC | VOID, SEE DOCKET NO. 27173, ITEM NO. 20 |
17 | 1/31/2003 | CENTRAL RECORDS | PC | VOID, SEE DOCKET NO. 27173, ITEM NO. 21 |
18 | 1/31/2003 | CENTRAL RECORDS | PC | VOID, SEE DOCKET NO. 27173, ITEM NO. 22 |
19 | 1/31/2003 | CENTRAL RECORDS | PC | VOID, SEE DOCKET NO. 27173, ITEM NO. 23 |
20 | 1/31/2003 | CENTRAL RECORDS | PC | VOID, SEE DOCKET NO. 27173, ITEM NO. 24 |
21 | 1/31/2003 | CENTRAL RECORDS | PC | VOID, SEE DOCKET NO. 27173, ITEM NO. 25 |
22 | 1/31/2003 | CENTRAL RECORDS | PC | VOID, SEE DOCKET NO. 27173, ITEM NO. 26 |
23 | 1/31/2003 | CENTRAL RECODS | PC | VOID, SEE DOCKET NO. 27173, ITEM NO. 27 |
24 | 1/31/2003 | CENTRAL RECORDS | PC | VOID, SEE DOCKET NO. 27173, ITEM NO. 28 |
25 | 1/31/2003 | CENTRAL RECORDS | PC | VOID, SEE DOCKET NO. 27173, ITEM NO. 29 |
26 | 1/31/2003 | PUC POLICY DEVELOPMENT | PL | LETTER TO JOHN W. JACKSON STAFFORD EXPLAINING WAYS TO PARTICIPATE IN THIS DOCKET |
27 | 2/4/2003 | WILEY YOUNG | PC | LETTER IN SUPPORT OF TRANSMISSION ROUTE |
28 | 2/4/2003 | DARLENE WHITEHEAD | PC | LETTER IN SUPPORT OF TRANSMISSION ROUTE |
29 | 2/4/2003 | MIKE ADAMSON | PC | LETTER IN OPPOSITION TO TRANSMISSION ROUTE |
30 | 2/5/2003 | PUC LEGAL | PL | COMMISSION STAFF'S RESPONSE TO ORDER NO.1 |
31 | 2/7/2003 | PUC POLICY DEVELOPMENT | PL | EXPLANATION OF WAYS TO PARTICIPATE IN DOCKET - MIKE ADAMSON |
32 | 2/7/2003 | PUC POLICY DEVELOPMENT DIVISION | PL | LETTER TO MS. DARLENE WHITEHEAD RE: STATUS OF PROCEEDINGS |
33 | 2/7/2003 | PUC POLICY DEVELOPMENT DIVISION | PL | LETTER TO MR. WILEY YOUNG RE: STATUS OF PROCEEDINGS |
34 | 2/10/2003 | PUC POLICY DEVELOPMENT DIVISION | PL | ORDER NO. 2 ADDRESSING SUFFICIENCY OF APPLICATION AND NOTICE; ESTABLISHING PROCEDURAL SCHEDULE |
35 | 2/11/2003 | CITY OF COPPERAS COVE | PL | MOTION TO INTERVENE |
36 | 2/13/2003 | JAMES & GORDON MICKAN | PC | MOTION TO INTERVENE |
37 | 2/14/2003 | JOSE I. REYNA | PL | LETTER IN OPPOSITION TO TRANSMISSION ROUTE |
38 | 2/18/2003 | RUFUS O. HILL | PC | LETTER OPPOSING TRANSMISSION LINE ROUTES 2 & 3 |
39 | 2/21/2003 | PUC POLICY DEVELOPMENT DIVISION | PL | ORDER NO. 3 GRANTING MOTION TO INTERVENE OF CITY OF COPPERAS COVE |
40 | 2/24/2003 | NORMAN T. OPLINGER | PL | REQUEST TO INTERVENE |
41 | 2/26/2003 | JOSE I. REYNA, JR. | PC | COMMENT LETTER OPPOSING PROPOSED TRANSMISSION LINE |
42 | 2/26/2003 | RICHARD PRATTE | PC | LETTER IN SUPPORT OF TRANSMISSION ROUTE |
43 | 2/26/2003 | JAMES BERRY | PC | LETTER IN OPPOSITION OF TRANSMISSION ROUTE |
44 | 2/27/2003 | TEXAS YOUTH COMMISSION | PC | REQUEST TO BE KEPT UPDATED ON THE ABOVE STYLED PROCEEDING |
45 | 2/27/2003 | ANGELICA HAMMICK | PC | LETTER IN SUPPORT OF PREFERRED ROUTE. |
46 | 2/28/2003 | ONCOR ELECTRIC DELIVERY COMPANY | PL | SUPPLEMENTAL AFFIDAVIT PERTAINING TO THE PROVISION OF NOTICE TO CITIES, COUNTIES, NEIGHBORING UTILITIES AND LANDOWNERS |
47 | 3/3/2003 | PUC POLICY DEVELOPMENT | PL | EXPLANATION OF WAYS TO PARTICIPATE IN DOCKET - JOSE REYNA |
48 | 3/5/2003 | PUC POLICY DEVELOPMENT | PL | LETTER TO MS. HAMMACK: RULES TO BECOME AN INTERVENOR OR A PROTESTOR IN THIS DOCKET |
49 | 3/5/2003 | PUC POLICY DEVELOPMENT | PL | EXPLANATION OF WAYS TO PARTICIPATE IN DOCKET |
50 | 3/7/2003 | PUC POLICY DEVELOPMENT | PL | EXPLANATION OF WAYS TO PARTICIPATE IN DOCKET |
51 | 3/7/2003 | PUC POLICY DEVELOPMENT | PL | EXPLANATION OF WAYS TO PARTICIPATE IN DOCKET - HOWARD HICKMAN |
52 | 3/7/2003 | WILLIAM & LAURA LONG | PC | PROTEST LETTER |
53 | 3/7/2003 | PUC POLICY DEVELOPMENT | PL | EXPLANATION OF WAYS TO PARTICIPATE IN DOCKET - MS. JOAN HARRIS |
54 | 3/7/2003 | PUC POLICY DEVELOPMENT | PL | EXPLANATION OF WAYS TO PARTICIPATE IN DOCKET - MR. & MRS. ROBER CARTER |
55 | 3/7/2003 | PUC POLICY DEVELOPMENT | PL | EXPLANATION OF WAYS TO PARTICIPATE IN DOCKET - MR. EVERETTE WHITE |
56 | 3/7/2003 | PUC POLICY DEVELOPMENT | PL | EXPLANATION OF WAYS TO PARTICIPATE IN DOCKET - MR. RICHARD BURESS |
57 | 3/7/2003 | PUC POLICY DEVELOPMENT | PL | EXPLANATION OF WAYS TO PARTICIPATE IN DOCKET - MR.AND MRS. JIM DUNN |
58 | 3/7/2003 | PUC POLICY DEVELOPMENT | PL | EXPLANATION OF WAYS TO PARTICIPATE IN DOCKET - MR.AND MRS. TROY LANGSTON |
59 | 3/7/2003 | PUC POLICY DEVELOPMENT | PL | EXPLANATION OF WAYS TO PARTICIPATE IN DOCKET - THOMAS COCKRELL |
60 | 3/7/2003 | PUC POLICY DEVELOPMENT | PL | EXPLANATION OF WAYS TO PARTICIPATE IN DOCKET - JAMES WELLS |
61 | 3/7/2003 | PUC POLICY DEVELOPMENT | PL | EXPLANATION OF WAYS TO PARTICIPATE IN DOCKET - HEATHER RALEY |
62 | 3/7/2003 | PUC POLICY DEVELOPMENT | PL | EXPLANATION OF WAYS TO PARTICIPATE IN DOCKET - DANIELA RAMOS |
63 | 3/7/2003 | PUC POLICY DEVELOPMENT | PL | EXPLANATION OF WAYS TO PARTICIPATE IN DOCKET - JEAN JONES |
64 | 3/7/2003 | PUC POLICY DEVELOPMENT | PL | EXPLANATION OF WAYS TO PARTICIPATE IN DOCKET - SUSAN SMITH |
65 | 3/7/2003 | PUC POLICY DEVELOPMENT | PL | EXPLANATION OF WAYS TO PARTICIPATE IN DOCKET - NED ROEHRIG |
66 | 3/7/2003 | PUC POLICY DEVELOPMENT | PL | EXPLANATION OF WAYS TO PARTICIPATE IN DOCKET - JAMES BERRY |
67 | 3/7/2003 | PUC POLICY DEVELOPMENT | PL | EXPLANATION OF WAYS TO PARTICIPATE IN DOCKET - MIKE CONNER |
68 | 3/7/2003 | PUC LEGAL | PL | COMMISSION STAFF'S RESPONSE TO ORDER NO. 2 |
69 | 3/7/2003 | PUC POLICY DEVELOPMENT | PL | ORDER NO. 4 GRANTING MOTION TO INTERVENE OF NORMAN OPLINGER; REQUIRING INFORMATION FROM RUFUS O. HILL |
70 | 3/12/2003 | PUC POLICY DEVELOPMENT | PL | ORDER NO. 5 ADDRESSING NOTICE COMPLIANCE; APPROVING ADDENDUM TO PROCEDURAL SCHEDULE |
71 | 3/18/2003 | RUFUS & INGE HILL FAMILY TRUST | PL | ADDITIONAL INFORMATION FOR MOTION TO INTERVENE |
72 | 3/20/2003 | ONCOR ELECTRIC DELIVERY COMPANY | PL | MOTION FOR REFERRAL TO SOAH |
73 | 3/21/2003 | PUC POLICY DEVELOPMENT DIVISION | PL | ORDER NO. 6 GRANTING MOTION TO INTERVENE OF RUFUS O. HILL ON BEHALF OF THE RUFUS O. HILL TRUST |
74 | 3/24/2003 | PUC POLICY DEVELOPMENT | PL | ORDER NO. 7 GRANTING MOTION TO INTERVENE OF JAMES AND GORDON MICKAN |
75 | 3/25/2003 | PUC POLICY DEVELOPMENT DIVISION | PL | Order of Referral |
76 | 3/28/2003 | SOAH | PL | ORDER NO.8 NOTICE OF PREHEARING CONFERENCE |
77 | 4/10/2003 | JIM AND ELLEN DUNN | PL | MOTION TO INTERVENE |
78 | 4/17/2003 | MIKE ADAMSON | PC | LETTER IN FAVOR OF PREFERRED TRANSMISSION LINE |
79 | 4/18/2003 | BOBBIE & WILEY YOUNG | PL | REQUEST TO INTERVENE |
80 | 4/18/2003 | DARLENE WHITEHEAD | PL | REQUEST TO INTERVENE |
81 | 4/24/2003 | KENNEDY REPORTING SERVICE | PL | TRANSCRIPT - PREHEARING CONFERENCE, MONDAY, APRIL 7, 2003, 10:15 A.M., PAGES 1 - 12 |
82 | 4/25/2003 | ONCOR ELECTRIC DELIVERY COMPANY | PL | REQUESTED MAP SHOWING PREFFERED AND ALTERNATIVE ROUTES FOR TRANSMISSION LINE |
83 | 4/30/2003 | SOAH | PL | ORDER NO. 10 GRANTING THE MOTIONS TO INTERVENE |
84 | 5/5/2003 | SOAH | PL | ORDER NO. 9 MEMORIALIZING PREHEARING CONFERENCE AND NOTICE OF HEARING |
85 | 5/15/2003 | E. ALLEN NYE, JR | PL | PARTIES OF RECORD HAVE AGREED TO MOVE THE CONFERENCE DATE, LOCATION, AND TIME |
86 | 6/4/2003 | JIM AND ELLEN DUNN | PL | JOINT MOTION TO CHANGE PROCEDURAL SCHEDULE |
87 | 6/11/2003 | SOAH | PL | ORDER NO. 11: GRANTING JOINT MOTION TO CHANGE PROCEDURAL SCHEDULE |
88 | 6/16/2003 | ONCOR ELECTRIC DELIVERY COMPANY | PL | AGREED MOTION FOR EXTENSION OF PROCEDURAL SCHEDULE AND REQUEST FOR EXPEDITED CONSIDERATION THEREOF |
89 | 6/18/2003 | SOAH | PL | ORDER NO. 12 GRANTING AGREED MOTION TO CHANGE PROCEDURAL SCHEDULE |
90 | 6/24/2003 | ONCOR ELECTRIC DELIVERY CO. | TEST | Direct Testimony of Larry Reiter |
91 | 6/24/2003 | ONCOR ELECTRIC DELIVERY CO. | TEST | Direct Testimony of Charles Jasper |
92 | 6/24/2003 | ONCOR ELECTRIC DELIVERY CO. | TEST | Direct Testimony of Cyril Welter |
93 | 6/27/2003 | PUC LEGAL & ENFORCEMENT | RFI | COMMISSION STAFF'S 1ST SET OF RFIS TO ONCOR ELECTRIC DELIVERY COMPANY REQUEST NO. TM-01 |
94 | 7/2/2003 | MR. AND MRS. DUNN | RFI | 1ST RFI TO ONCOR ELECTRIC DELIVERY COMPANY |
95 | 7/7/2003 | DARLENE WHITEHEAD | PC | REAFFIRMATION LETTER |
96 | 7/11/2003 | WILEY AND BOBBIE YOUNG | PC | LETTER IN SUPPORT OF THE PREFERRED ROUTE |
97 | 7/11/2003 | MR. AND MRS. DUNN | RFI | 2ND RFI TO ONCOR ELECTRIC DELIVERY COMPANY |
98 | 7/17/2003 | SOAH | PL | ORDER NO. 13 CANCELING PREHEARING CONFERENCE SET FOR JULY 22, 2003 |
99 | 7/18/2003 | ONCOR ELECTRIC DELIVERY COMPANY | RFI | RESPONSE TO PUC STAFF'S 1ST RFI |
100 | 7/18/2003 | MR. AND MRS. DUNN | PL | AGREED MOTION TO EXTEND PROCEDURAL SCHEDULE AND REQUEST FOR EXPEDITED CONSIDERATION |
101 | 7/21/2003 | CALVIN & FREDIA WEAVER | PC | PROTEST LETTER |
102 | 7/22/2003 | ONCOR ELECTRIC DELIVERY COMPANY | RFI | RESPONSE TO DUNN'S 1ST RFI |
103 | 7/23/2003 | PUC POLICY DEVELOPMENT | PL | ORDER NO. 14: GRANTING AGREED MOTION TO CHANGE PROCEDURAL SCHEDULE |
104 | 7/29/2003 | MR. AND MRS. DUNN | PL | AGREED MOTION FOR LIMITED AMEND THE PROCEDURAL SCHEDULE AND REQUEST FOR EXPEDITED CONSIDERATION |
105 | 7/31/2003 | SOAH | PL | ORDER NO. 15: GRANTING AGREED MOTION TO CHANGE PROCEDURAL SCHEDULE |
106 | 8/1/2003 | DUNN | TEST | Dunn Testimony |
107 | 8/1/2003 | MR. AND MRS. DUNN | TEST | DIRECT TESTIMONY OF ALLISON ARNOLD |
108 | 8/4/2003 | ONCOR ELECTRIC DELIVERY COMPANY | RFI | RESPONSE OF ONCOR ELECTRIC DELIVERY COMPANY TO DUNN'S SECOND REQUEST FOR INFORMATION |
109 | 8/8/2003 | ONCOR ELECTRIC DELIVERY COMPANY | PL | OBJECTIONS OF ONCOR ELECTRIC DELIVERY COMPANY TO THE PREFILED DIRECT TESTIMONY OF ELLEN FUNN |
110 | 8/15/2003 | PUC LEGAL & ENFORCEMENT | PL | STAFF'S STATEMENT OF POSITION |
111 | 8/15/2003 | MR. AND MRS. DUNN'S | PL | RESPONSE TO OBJECTIONS OF ONCOR ELECTRIC DELIVERY COMPANY TO THE PREFILED TESTIMONY OF ELLEN DUNN |
112 | 8/28/2003 | ONCOR ELECTRIC DELIVERY CO. | RFI | ONCOR ELECTRIC DELIVERY COMPANY'S FIRST REQUEST FOR INFORMATION FROM ELLEN AND JIM DUNN |
113 | 9/2/2003 | MR. AND MRS. DUNN | RFI | 3RD RFI TO ONCOR ELECTRIC DELIVERY COMPANY |
114 | 9/5/2003 | ONCOR ELECTRIC DELIVERY CO. | TEST | REBUTTAL TESTIMONY OF CHARLES T JASPER |
115 | 9/10/2003 | COPPERAS COVE ISD | PL | clarification letter |
116 | 9/10/2003 | CITY OF COPPERAS COVE | PL | NOTICE OF INTENTION TO CROSS-EXAMINE INTERVENOR WITNESSES |
117 | 9/15/2003 | MR. AND MRS. DUNN | PL | RESPONSE TO NOTICE OF INTENT TO CROSS-EXAMINE INTERVENOR WITNESSES |
118 | 9/16/2003 | MR. AND MRS. DUNN | RFI | 4TH RFI TO ONCOR ELECTRIC DELIVERY COMPANY |
119 | 9/16/2003 | CITY OF COPPERAS COVE | PL | REPLY TO DUNNS' OBJECTION TO CROSS-EXAMINATION BY THE CITY OF COPPERAS COVE |
120 | 9/22/2003 | ONCOR ELECTRIC DELIVERY COMPANY | RFI | RESPONSE TO DUNN'S 3RD RFI |
121 | 9/22/2003 | ONCOR ELECTRIC DELIVERY COMPANY | RFI | SUPPLEMENTAL RESPONSE TO DUNN'S 1ST RFI |
122 | 9/22/2003 | MR. AND MRS. DUNN'S | RFI | RESPONSE TO ONCOR ELECTRIC DELIVERY COMPANY'S FIRST RFI'S |
123 | 9/25/2003 | J W C, INC. | PL | REQUEST TO INTERVENE |
124 | 9/25/2003 | ONCOR ELECTRIC DELIVERY CO. | PL | OBJECTIONS OF ONCOR ELECTRIC DEIVERY COMPANY TO THE DUNN'S 4TH SET OF RFI'S |
125 | 9/26/2003 | ONCOR ELECTRIC DELEVERY COMPANY | RFI | RESPONSE OF ONCOR ELECTRIC DELIVERY COMPANY TO DUNN'S FOURTH REQUEST FOR INFORMATION |
126 | 9/26/2003 | ONCOR ELECTRIC DELIVERY COMPANY | RFI | SUPPLEMENTAL RESPONSE TO DUNN'S 3RD RFI |
127 | 9/29/2003 | ONCOR ELECTRIC DELIVERY CO. | RFI | SUPPLEMENTAL RESPONSE TO ONCOR ELECTRIC DELIVERY COMPANY TO DUNN'S THIRD RFI |
128 | 9/29/2003 | TOWN SQUARE SHOPPING CENTER | PC | PROPOSED ALTERNATIVE ROUTE 4 |
129 | 9/29/2003 | WESLEY ATKINSON | PC | LETTER IN OPPOSITION TO TRANSMISSION ROUTE NUMBER 4 |
130 | 9/29/2003 | ATKINSON ELECTRIC INC. | PC | LETTER IN OPPOSITION TO TRANSMISSION ROUTE NUMBER 4 |
131 | 9/29/2003 | MIKE ATKINSON | PC | LETTER IN OPPOSITION TO THE TRANSMISSION ROUTE NUMBER 4 |
132 | 9/29/2003 | CLEAR CREEK CONSTRUCTION, INC. | PC | LETTER IN OPPOSITION TO THE ALTERNATIVE ROUTE NUMBER 4 |
133 | 9/29/2003 | NEIMAN'S PLUMBING & A/C, INC. | PC | LETTER IN OPPOSITION TO THE ALTERNATIVE ROUTE NUMBER 4 |
134 | 9/29/2003 | CLEAR CREEK BAPTIST CHURCH | PC | LETTER IN OPPOSITION TO THE ALTERNATIVE ROUTE NUMBER 4 |
135 | 9/29/2003 | HOUSING AUTHORITY OF THE CITY OF COPPERAS COVE | PC | OPPOSITION LETTER RE: TRANSMISSION ROUTE |
136 | 9/29/2003 | TURLEY ASSOCIATES | PC | OPPOSITION LETTER RE: TRANSMISSION ROUTE |
137 | 9/29/2003 | WALKER PLACE III SUBDIVISION | PC | OPPOSITION LETTER RE: TRANSMISSION ROUTE |
138 | 9/30/2003 | ANDREA HOWARD | PC | OPPOSITION LETTER RE: TRANSMISSION ROUTE IN BELL AND CORYELL COUNTIES |
139 | 9/30/2003 | BEVERLY SMITH | PC | OPPOSITION LETTER RE: TRANSMISSION ROUTE IN BELL AND CORYELL COUNTIES |
140 | 9/30/2003 | CATHIE D. ELDER | PC | OPPOSITION LETTER RE: TRANSMISSION ROUTE IN BELL AND CORYELL COUNTIES |
141 | 9/30/2003 | PAUL M. BOYER | PC | OPPOSITION LETTER RE: TRANSMISSION ROUTE |
142 | 9/30/2003 | PAUL & MARGARET FLEET | PC | LETTER IN OPPOSITION TO THE ALTERNATIVE ROUTE NUMBER 4 |
143 | 10/3/2003 | JAMES R. ANDERSON, CHANCELLOR | PL | TESTIMONY OF ELLEN DUNN IS NO EMPOWERED TO SPEAK FOR THE COLLEGE IN THIS MATTER, COLLEGE HAS NO POSITION REGARDING THE PLACEMENT OF THE PROPOSED TRANSMISSION LINE |
144 | 10/17/2003 | KENNEDY REPORTING SERVICE | PL | HEARING ON THE MERITS MONDAY, SEPTEMBER 29, 2003 10:15 A.M., (VOLUME 1, PAGES 1-186) |
145 | 10/17/2003 | KENNEDY REPORTING SERVICE | PL | HEARING ON THE MERITS TUESDAY, SEPTEMBER 30, 2003 9:05 A.M., (VOLUME 2, PAGES 187-457) |
146 | 10/30/2003 | ONCOR ELECTRIC DELEVERY COMPANY | BR | INITIAL BRIEF |
147 | 10/30/2003 | COPPERAS COVE | BR | Initial Brief |
148 | 10/30/2003 | PUC LEGAL & ENFORCEMENT | BR | STAFF'S INITIAL POST-HEARING BRIEF |
149 | 10/30/2003 | MR. AND MRS DUNN | BR | Initial Brief |
150 | 11/12/2003 | KENNEDY REPORTING SERVICE | PL | ENCLOSED UNDER SEPARATE COVER ARE THE FOLLOWING DOCUMENTS |
151 | 11/14/2003 | ONCOR ELECTRIC DELiVERY COMPANY | BR | REPLY BRIEF |
152 | 11/14/2003 | MR. AND MRS. DUNN | BR | Reply Brief |
153 | 11/14/2003 | PUC LEGAL & ENFORCEMENT | BR | STAFF'S REPLY BRIEF |
154 | 11/14/2003 | CITY OF COPPERAS COVE | BR | City of Copperas Cove's Reply Brief |
155 | 12/30/2003 | SOAH | PL | ORDER NO.16; EXTENDING DEADLINE |
156 | 1/9/2004 | POLICY DEVELOPMENT | PL | Proposal for Decision |
157 | 1/12/2004 | POLICY DEVELOPMENT | PL | Exceptions and Replies Deadlines Memo for PFD |
158 | 1/14/2004 | SOAH | PL | LETTER TO OPD RE : RETURN OF EXHIBITS AND TRANSCRIPTS |
159 | 1/16/2004 | ONCOR ELECTRIC DELIVERY CO. | PL | EXCEPTIONS TO THE PROPOSAL FOR DECISION |
160 | 1/16/2004 | PUC LEGAL | PL | NOTICE THAT STAFF WILL NOT BE FILING EXCEPTIONS TO THE PROPOSAL FOR DECISION ISSUED JANUARY, 12, 2004 |
161 | 1/16/2004 | DUNN | PL | Exceptions |
162 | 1/20/2004 | ONCOR ELECTRIC DELEVERY COMPANY | PL | RESPONSE TO EXCEPTIONS |
163 | 1/20/2004 | CITY OF COPPERAS COVE | PL | City of Copperas Cove's Reply to Dunns' Exceptions |
164 | 1/20/2004 | JIM AND ELLEN DUNN | PL | MR. AND MRS. DUNN'S REPLY TO EXCEPTIONS |
165 | 1/20/2004 | PUC LEGAL & ENFORCEMENT | PL | Staff's Reply To Exceptions |
166 | 1/23/2004 | PUC POLICY DEVELOPMENT DIVISION | PL | OPEN MEETING, JANUARY 29, 2004, AGENDA ITEM NUMBER 8; DISCUSSION AND POOISBLE ACTION WITH REGARDS TO PRELIMINARY ORDER |
167 | 2/3/2004 | PUC POLICY DEVELOPMENT DIVISION | PL | Order |
168 | 2/26/2004 | DUNN | PL | Motion for Rehearing |
169 | 3/3/2004 | PUC POLICY DEVELOPMENT DIVISION | PL | MOTION FOR REHEARING TO AN OPEN MEETING AGENDA |
170 | 4/28/2004 | PUC POLICY DEVELOPMENT DIVISION | PL | REQUEST FOR REPRESENTATION BY THE ATTORNEY GENERAL IN THE LAWSUIT OF THE DUNN'S VS. PUC |
171 | 9/13/2004 | ENEIDA & ROBERTO AYALA | PL | REQUEST TO INTERVENE |
172 | 9/15/2004 | JAY & ENDINA MCCAULEY | PL | REQUEST TO INTERVENE |
173 | 9/20/2004 | LUIS OQUENDO | PL | REQUEST TO INTERVENE |
174 | 3/8/2005 | PUC POLICY DEVELOPMENT | EX | DUNN EXHIBITS #1-10, 15-29, & 31-33 |
175 | 3/8/2005 | PUC POLICY DEVELOPMENT | EX | MICKAN EXHIBITS #1 |
176 | 3/8/2005 | PUC POLICY DEVELOPMENT | EX | ONCOR EXHIBITS #1-6 |
177 | 3/8/2005 | PUC POLICY DEVELOPMENT | EX | STAFF EXHIBITS #1 |
178 | 9/12/2006 | PUC CADM | EX | ONCOR EXHIBITS #2 (2 MAP BOARDS) |
179 | 12/21/2018 | CENTRAL RECORDS | PL | SENT OFFSITE TO THE STATE RECORDS CENTER 12/2018 |