Filings for 16774
Case Style SOUTHWESTERN ELECTRIC POWER COMPANY REPORT PURSUANT TO SUBST. R. 23.31(c)(2)(D)(vi) REGARDING ACTIVITIES FOR WHICH A CERTIFICATE OF CONVENIENCE AND NECESSITY IS NOT NECESSARY (REBUILD SWEPCO LONE STAR SOUTH PITTSBURG 138KV FEEDER)
4 filing(s).
Item | File Stamp | Party | Item Type | Filing Description |
---|---|---|---|---|
1 | 12/12/1996 | SWEPCO | PL | SOUTHWESTERN ELECTRIC POWER COMPANY REPORT PURSUANT TO SUBST. R. 23.31(c)(2)(D)(vi) REGARDING ACTIVITIES FOR WHICH A CERTIFICATE OF CONVENIENCE AND NECESSITY IS NOT NECESSARY (REBUILD SWEPCO LONE STAR SOUTH PITTSBURG 138KV FEEDER) |
2 | 12/31/1996 | GC | PRJ | LETTER TO CSW RE : DESCRIBED ACTIVITIES FALL WITHIN SUB RULE 23.31 AND DO NOT REQUIRE A CCN |
3 | 1/10/1997 | SWEPCO | PL | ADDITIONS TO THE PROPOSED TRANSMISSION LINE REBUILDING PROJECT |
4 | 3/2/2007 | CENTRAL RECORDS | PRJ | PURGED (3/07) |
Export to Excel |