Filings for 16774



Case Style   SOUTHWESTERN ELECTRIC POWER COMPANY REPORT PURSUANT TO SUBST. R. 23.31(c)(2)(D)(vi) REGARDING ACTIVITIES FOR WHICH A CERTIFICATE OF CONVENIENCE AND NECESSITY IS NOT NECESSARY (REBUILD SWEPCO LONE STAR SOUTH PITTSBURG 138KV FEEDER)

4 filing(s).

Item File Stamp Party Item Type Filing Description
1 12/12/1996 SWEPCO PL SOUTHWESTERN ELECTRIC POWER COMPANY REPORT PURSUANT TO SUBST. R. 23.31(c)(2)(D)(vi) REGARDING ACTIVITIES FOR WHICH A CERTIFICATE OF CONVENIENCE AND NECESSITY IS NOT NECESSARY (REBUILD SWEPCO LONE STAR SOUTH PITTSBURG 138KV FEEDER)
2 12/31/1996 GC PRJ LETTER TO CSW RE : DESCRIBED ACTIVITIES FALL WITHIN SUB RULE 23.31 AND DO NOT REQUIRE A CCN
3 1/10/1997 SWEPCO PL ADDITIONS TO THE PROPOSED TRANSMISSION LINE REBUILDING PROJECT
4 3/2/2007 CENTRAL RECORDS PRJ PURGED (3/07)
Export to Excel