Filings for 15152
Case Style PETITION FOR EXPANDED LOCAL CALLING SERVICE FROM THE BOGATA EXCHANGE TO THE WINNSBORO, WINFIELD, CLARKSVILLE, MT. VERNON, AND TALCO EXCHANGES
28 filing(s).
Item | File Stamp | Party | Item Type | Filing Description |
---|---|---|---|---|
1 | 12/21/1995 | LEGAL ADMIN | PRJ | ORDER NO. 1: ESTABLISHING PROJECT AND PROCEDURAL SCHEDULE |
2 | 1/26/1996 | GTE | PRJ | REQUEST FOR AN EXTENSION OF THE PROCEDURAL SCHEDULE |
3 | 1/29/1996 | LEGAL ADMIN | PRJ | ORDER NO. 2: GRANTING EXTENSION OF TIME |
4 | 2/5/1996 | GC | PRJ | MEMO TO EXAMINER COWAN RE : INFORMATION OFFERED TO HELP EXPLAIN THE REASON FOR GTE'S REQUEST TO EXTEND THE TIMELINE FOR 30 DAYS |
5 | 2/20/1996 | GC | PRJ | STAFF RECOMMENDATION TO REQUEST THAT PETITIONING EXCHANGE FEES AND IMPLEMENTATION SCHEDULE BE FILED |
6 | 2/21/1996 | RA | PRJ | STAFF RECOMMENDATION TO WITHDRAW REQUEST THAT PETITIONING EXCHANGE FEES AND IMPLEMENTATION SCHEDULE BE FILED |
7 | 3/5/1996 | GTE | PRJ | LETTER TO EXAMINER COWAN RE : A FURTHER EXTENSION |
8 | 3/6/1996 | LEGAL ADMIN | PRJ | ORDER NO. 3: GRANTING EXTENSION OF TIME |
9 | 4/25/1996 | LEGAL ADMIN | PRJ | ORDER #4 : REQUIRING LEC TO FILE COST STUDIES |
10 | 4/26/1996 | GTE | PRJ | LETTER TO EXAMINER COWAN RE : EXTENSION FOR IFLING COST STUDIES |
11 | 4/30/1996 | LEGAL ADMIN | PRJ | ORDER NO. 5: GRANTING EXTENSION OF TIME |
12 | 5/9/1996 | GTE | PRJ | LETTER TO EXAMINER COWAN RE : THE BOGATA EXCHANGE |
13 | 5/20/1996 | CONTEL | PRJ | COST DOCUMENTATION AND IMPLEMENTATION SCHEDULE FOR THE INTERLATA ROUTE FROM BOGATA TO CLARKSVILLE, MT. VERNON, TALCO, WINNSBORO, AND WINFIELD |
14 | 5/22/1996 | LEGAL ADMIN | PRJ | ORDER #6 : REQUIRING AMENDED COST DOCUMENTATION |
15 | 6/12/1996 | PEOPLES TELEPHONE COOP | PRJ | AMENDED COST DOCUMENTATION |
16 | 6/13/1996 | LEGAL ADMIN | PRJ | ORDER #7 : REQUIRING LEC TO FILE COST STUDIES |
17 | 6/20/1996 | GTE | PRJ | LETTER TO EXAMINER COWAN RE : COST STUDIES AND IMPLEMENTATION SCHEDULE FOR THE BOGATA EXCHANGE |
18 | 7/15/1996 | LEGAL ADMIN | PRJ | ORDER NO. 8: GRANTING INTERIM APPROVAL OF PROPOSED FEES AND IMPLEMENTATION SCHEDULE |
19 | 7/17/1996 | GC | PRJ | STAFF FINAL RECOMMENDATION OF PETITIONING EXCHANGE FEES AND IMPLEMENTATION SCHEDULE |
20 | 7/18/1996 | GTE | PRJ | TARIFF SHEET |
21 | 7/19/1996 | GC | PRJ | STAFF RECOMMENDATION FOR CORRECTION OF TARIFF SHEET REVISION |
22 | 7/22/1996 | LEGAL ADMIN | PRJ | ORDER #9 : REQUIRING LEC TO FILE AMENDED TARIFF SHEETS |
23 | 8/1/1996 | GTE | PRJ | TARIFF SHEETS |
24 | 8/7/1996 | RA | PRJ | STAFF RECOMMENDATION FOR APPROVAL OF TARIFF SHEET REVISION |
25 | 8/8/1996 | LEGAL ADMIN | PRJ | ORDER NO. 10: GRANTING FINAL APPROVAL AND SEVERING ISSUES RELATING TO EXCESS COSTS AND LOST REVENUE |
26 | 10/10/1996 | GTE | PRJ | LETTER TO EXAMINER COWAN RE : STATUS REPORT |
27 | 1/11/2007 | CENTRAL RECORDS | PRJ | PURGED (1/07) |
28 | 7/31/2014 | CENTRAL RECORDS | PRJ | BOOK FILE |
Export to Excel |