Filings for 52440
Case Style APPLICATION OF CRYSTAL SPRINGS WATER COMPANY, INC. TO AMEND ITS WATER CERTIFICATE OF CONVENIENCE AND NECESSITY IN MONTGOMERY COUNTY
39 filing(s).
Item | File Stamp | Party | Item Type | Filing Description |
---|---|---|---|---|
1 | 8/17/2021 | Crystal Springs Water Co., Inc. | PL | APPLICATION OF CRYSTAL SPRINGS WATER COMPANY, INC. TO AMEND ITS CERTIFICATES OF CONVENIENCE AND NECESSITY IN MONTGOMERY COUNTY |
2 | 8/18/2021 | CRYSTAL SPRINGS WATER CO. INC. | CONF | Confidential- Financial Information Bate Stamp- 1 to 139 |
3 | 8/20/2021 | PUC OPDM | PL | ORDER NO. 1 - REQUIRING COMMENTS ON ADMINISTRATIVE COMPLETENESS AND PROPOSED NOTICE, ENTERING PROTECTIVE ORDER, AND ADDRESSING OTHER PROCEDURAL MATTERS |
4 | 8/25/2021 | CRYSTAL SPRINGS WATER CO. INC. | MAPS | revised maps and shp files |
5 | 9/16/2021 | PUC LEGAL | RFI | COMMISSION STAFF’S FIRST REQUEST FOR INFORMATION CRYSTAL SPRINGS WATER COMPANY, INC. QUESTION NO. STAFF 1-1 |
6 | 9/16/2021 | PUC LEGAL | PL | COMMISSION STAFF’S RECOMMENDATION ON ADMINISTRATIVE COMPLETENESS AND NOTICE AND PROPOSED PROCEDURAL |
7 | 9/16/2021 | PUC OPDM | PL | ORDER NO. 2 - FINDING APPLICATION ADMINISTRATIVELY COMPLETE, PROPOSED NOTICE SUFFICIENT, AND ESTABLISHING PROCEDURAL SCHEDULE |
8 | 10/7/2021 | Crystal Springs Water Co., Inc. | MISC | Neighbor Notices, Tear Sheets and Affidavits |
9 | 11/10/2021 | PUC LEGAL | PL | COMMISSION STAFF’S RECOMMENDATION ON SUFFICIENCY OF NOTICE AND PROPOSED PROCEDURAL SCHEDULE |
10 | 11/10/2021 | CRYSTAL SPRINGS WATER CO. INC. | MISC | Additional information |
11 | 11/10/2021 | PUC LEGAL | RFI | COMMISSION STAFF’S SECOND REQUEST FOR INFORMATION CRYSTAL SPRINGS WATER COMPANY, INC. QUESTION NO. STAFF 2-1 THROUGH 2-3 |
12 | 11/12/2021 | PUC LEGAL | PL | COMMISSION STAFF’S SUPPLEMENTAL RECOMMENDATION ON SUFFICIENCY OF NOTICE AND PROPOSED PROCEDURAL SCHEDULE |
13 | 11/12/2021 | PUC OPDM | PL | ORDER NO. 3-FINDING NOTICE SUFFICIENT AND ADOPTING PROCEDURAL SCHEDULE |
14 | 12/1/2021 | Crystal Sjprings Water Co., Inc. | MISC | Response to First RFI |
15 | 12/15/2021 | PUC LEGAL | PL | COMMISSION STAFF’S REQUEST FOR EXTENSION AND ABATEMENT OF PROCEDURAL SCHEDULE |
16 | 12/29/2021 | PUC OPDM | PL | ORDER NO. 4 - GRANTING EXTENSION AND ABATEMENT OF PROCEDURAL SCHEDULE |
17 | 1/17/2022 | CRYSTAL SPRINGS WATER CO., INC. | MISC | Bank Letter |
18 | 1/31/2022 | PUC LEGAL | PL | COMMISSION STAFF’S THIRD REQUEST FOR INFORMATION CRYSTAL SPRINGS WATER COMPANY, INC. QUESTION NOS. STAFF 3-1 THROUGH 3-4 |
19 | 4/14/2022 | PUC OPDM | PL | ORDER NO. 5 - REQUIRING STATUS REPORT |
20 | 4/26/2022 | CRYSTAL SPRINGS WATER CO. INC. | MISC | Response to second request for information |
21 | 4/27/2022 | CRYSTAL SPRINGS WATER CO. INC. | MISC | Response to Third Request for Information |
22 | 5/6/2022 | PUC LEGAL | PL | JOINT STATUS REPORT |
23 | 5/17/2022 | PUC OPDM | PL | ORDER NO. 6 - REQUIRING STATUS REPORT |
24 | 6/29/2022 | CRYSTAL SPRINGS WATER CO. INC. | MISC | first phase distribution system approval from TCEQ |
25 | 7/5/2022 | CRYSTAL SPRINGS WATER CO. INC. | MISC | Supplemental Responses to Staff's 3-3 and 3-4 |
26 | 7/8/2022 | PUC LEGAL | PL | JOINT SUPPLEMENTAL STATUS REPORT |
27 | 7/8/2022 | Crystal Springs | MISC | TCEQ approval of section 2 distribution system |
28 | 7/12/2022 | PUC OPDM | PL | ORDER NO. 7 - REQUIRING STATUS REPORT |
29 | 7/18/2022 | PUC LEGAL | PL | JOINT MOTION TO SEVER AND ABATE, REQUEST TO RESTYLE THE DOCKET, AND PROPOSED PROCEDURAL SCHEDULE |
30 | 7/21/2022 | PUC OPDM | PL | ORDER NO. 8 - SEVERING PROCEEDINGS, RESTYLING DOCKET, AND ESTABLISHING PROCEDURAL SCHEDULE |
31 | 7/26/2022 | CRYSTAL SPRINGS WATER CO. INC. | MAPS | Water service area maps only (due to severance of the docket between water and sewer) |
32 | 8/8/2022 | CRYSTAL SPRINGS WATER CO. INC. | MISC | Consent Form, Approval to Use Letter from TCEQ, Cover letter of explanation. |
33 | 8/8/2022 | CRYSTAL SPRINGS WATER CO. INC. | ADMN | Letter of explanation, Signed consent form, TCEQ approval to use letter for interconnect between Timberland Estates and Rolling HIlls Oaks Water systems |
34 | 8/18/2022 | PUC LEGAL | PL | COMMISSION STAFF’S FINAL RECOMMENDATION |
35 | 9/1/2022 | PUC LEGAL | PL | JOINT MOTION TO ADMIT EVIDENCE AND PROPOSED NOTICE OF APPROVAL |
36 | 9/9/2022 | PUC OPDM | PL | ORDER NO. 9 - ADMITTING EVIDENCE |
37 | 9/20/2022 | PUC OPDM | PL | NOTICE OF APPROVAL |
38 | 9/30/2022 | PUC LEGAL | TARF | Memorandum with Approved Tariff. |
39 | 10/5/2022 | PUC CENTRAL RECORDS | TARF | STAMPED APPROVED TARIFF |
Export to Excel |