Case Style   APPLICATION OF EL PASO ELECTRIC COMPANY FOR APPROVAL TO ADJUST ITS ENERGY EFFICIENCY COST RECOVERY FACTOR AND REQUEST FOR REVISED COST CAP

22 filing(s).

Item File Stamp Party Filing Description
1 4/26/2016 EL PASO ELECTRIC COMPANY REQUEST OF EL PASO ELECTRIC COMPANY FOR A DOCKET NUMBER WITH THE FOLLOWING STYLE: APPLICATION OF EL PASO ELECTRIC COMPANY TO ADJUST ITS ENERGY EFFICIENCY COST RECOVERY FACTOR AND REQUEST FOR REVISED COST CAP
2 4/29/2016 EL PASO ELECTRIC COMPANY CONFIDENTIAL - EXHIBIT AGP-09, LIST OF ENERGY EFFICIENCY SERVICE PROVIDERS; BATE STAMP: 1 to 5
3 4/29/2016 EL PASO ELECTRIC COMPANY APPLICATION OF EL PASO ELECTRIC COMPANY FOR APPROVAL TO ADJUST ITS ENERGY EFFICIENCY COST RECOVERY FACTOR AND REQUEST FOR REVISED COST CAP
4 5/2/2016 PUC CADM ORDER OF REFERRAL
5 5/5/2016 CITY OF EL PASO MOTION TO INTERVENE
6 5/5/2016 SOAH SOAH ORDER NO. 1 DESCRIPTION OF CASE; REQUIRING STAFF COMMENT ON SUFFICIENCY OF NOTICE; ADOPTING PROCEDURAL SCHEDULE; AND ADOPTING PROTECTIVE ORDER
7 5/6/2016 TEXAS INDUSTRIAL ENERGY CONSUMERS MOTION TO INTERVENE
8 5/9/2016 PUC LEGAL COMMISSION STAFF'S LIST OF ISSUES
9 5/9/2016 EL PASO ELECTRIC COMPANY PROPOSED LIST OF ISSUES
10 5/10/2016 EL PASO ELECTRIC COMPANY Proof of Notice
11 5/11/2016 PUC LEGAL COMMISSION STAFF'S COMMENTS ON SUFFICIENCY OF APPLICATION AND NOTICE
12 5/12/2016 PUC CADM DRAFT PRELIMINARY ORDER
13 5/19/2016 PUC LEGAL COMMISSION STAFF'S 1ST RFI TO EL PASO ELECTRIC COMPANY QUESTION NOS. STAFF 1-1 THROUGH STAFF 1- 3
14 5/19/2016 PUC LEGAL COMMISSION STAFF'S 1ST RFI TO CITY OF EL PASO QUESTION NOS. STAFF 1-1 THROUGH STAFF 1- 3
15 5/23/2016 PUC CADM PRELIMINARY ORDER
16 5/23/2016 PUC CADM OUTGOING COMMISSION-SIGNED ORDER MAIL LOG
17 5/26/2016 CITY OF EL PASO REQUEST FOR HEARING
18 5/31/2016 EL PASO ELECTRIC COMPANY RESPONSE TO COMMISSION STAFF'S FIRST RFI QUESTION NOS. STAFF1-1 THROUGH 1-3
19 6/3/2016 EL PASO ELECTRIC COMPANY AGREED SCHEDULE
20 6/6/2016 SOAH SOAH ORDER NO. 2 GRANTING MOTIONS TO INTERVEN E, ADOPTING PROCEDURAL SCHEDULE AND NOTICE OF HEARING
21 6/7/2016 CITY OF EL PASO RESPONSES TO COMMISSION STAFF'S FIRST RFI QUESTION NOS. STAFF 1-1 THROUGH 1-3
22 6/30/2016 EL PASO ELECTRIC COMPANY Supplemental Testimony of Araceli G. Perea
Export to Excel