Filings for 40343
Case Style APPLICATION OF EL PASO ELECTRIC COMPANY FOR APPROVAL TO REVISE ITS ENERGY EFFICIENCY COST RECOVERY FACTOR AND REQUEST TO ESTABLISH REVISED GOALS AND COST CAPS
50 filing(s).
Item | File Stamp | Party | Item Type | Filing Description |
---|---|---|---|---|
28 | 5/30/2012 | CITY OF EL PASO | BR | BRIEF ON THRESHOLD LEGAL/ POLICY ISSUES |
29 | 5/30/2012 | EL PASO ELECTRIC COMPANY | BR | RESPONSE TO ORDER REQUESTING BRIEFING ON THRESHOLD LEGAL/ POLICY ISSUES |
30 | 5/30/2012 | PUC LEGAL | BR | STAFF'S BRIEF ON THRESHOLD LEGAL/POLICY ISSUES |
37 | 6/4/2012 | EL PASO ELECTRIC COMPANY | CONF | CONFIDENTIAL - RESPONSE TO STAFF 6-1 ATTACHMENT 1 : BATE STAMP : 1 CD |
19 | 5/21/2012 | EL PASO ELECTRIC COMPANY | CONF | CONFIDENTIAL- RESPONSE TO STAFF KC 3-3, ATTACHMENT 1; BATE STAMP: 1-4 |
32 | 5/30/2012 | SIERRA CLUB, LONE STAR CHAPTER | PC | COMMENTS |
33 | 5/31/2012 | PUC LEGAL | PL | COMMISSION STAFF'S PROPOSED PROCEDURAL SCHEDULE |
38 | 6/4/2012 | EL PASO ELECTRIC COMPANY | PL | STATEMENT UNDER SECTION 4 OF PROTECTIVE ORDER DESIGNATING CONFIDENTIAL AND HIGHLY SENSITIVE PROTECTED MATERIALS |
39 | 6/5/2012 | SOAH | PL | SOAH ORDER NO. 3 : PROTECTIVE ORDER |
40 | 6/6/2012 | SOAH | PL | SOAH ORDER NO. 2 : MEMORIALIZING PREHEARING CONFERENCE, GRANTING MOTIONS TO INTERVENE, REVISING PROCEDURAL SCHEDULE, AND NOTICE OF HEARING |
41 | 6/6/2012 | EL PASO ELECTRIC COMPANY | PL | STATEMENT UNDER SECTION 4 OF PROTECTIVE ORDER DESIGNATING CONFIDENTIAL AND HIGHLY SENSITIVE PROTECTED MATERIALS |
31 | 5/30/2012 | TEXAS INDUSTRIAL ENERGY CONSUMERS | PL | MOTION TO INTERVENE |
21 | 5/22/2012 | PUC CADM | PL | Preliminary Order |
22 | 5/22/2012 | PUC CADM | PL | OUTGOING COMMISSION - SIGNED ORDER MAIL LOG |
16 | 5/18/2012 | CITY OF EL PASO | PL | MOTION TO INTERVENE |
11 | 5/10/2012 | PUC CADM | PL | ORDER REQUESTING BRIEFING ON THRESHOLD LEGAL/ POLICY ISSUES |
12 | 5/11/2012 | PUC CADM | PL | OPEN MEETING, MAY 18, 2012; AGENDA ITEM No. 6; DRAFT PRELIMINARY ORDER |
13 | 5/11/2012 | EL PASO ELECTRIC COMPANY | PL | PROOF OF NOTICE |
14 | 5/16/2012 | PUC CADM | PL | Revised Draft Preliminary Order |
1 | 4/26/2012 | EL PASO ELECTRIC COMPANY | PL | REQUEST FOR ASSIGNMENT OF DOCKET NUMBER RE: APPLICATION OF EL PASO ELECTRIC COMPANY FOR APPROVAL TO REVISE ITS ENERGY EFFICIENCY COST RECOVERY FACTOR AND REQUEST TO ESTABLISH REVISED GOALS AND COST CAPS |
2 | 4/30/2012 | EL PASO ELECTRIC COMPANY | PL | APPLICATION OF EL PASO ELECTRIC COMPANY FOR APPROVAL TO REVISE ITS ENERGY EFFICIENCY COST RECOVERY FACTOR AND REQUEST TO ESTABLISH REVISED GOALS AND COST CAPS |
3 | 4/30/2012 | PUC CADM | PL | ORDER OF REFERRAL |
4 | 5/2/2012 | SOAH | PL | SOAH ORDER NO. 1: SETTING OUT PROCEDURAL SCHEDULE AND NOTICE OF PREHEARING CONFERENCE |
5 | 5/3/2012 | EL PASO ELECTRIC COMPANY | PL | CHANGE OF IT'S PROPOSED MANNER OF GIVING NOTICE |
6 | 5/7/2012 | PUC LEGAL | PL | COMMISSION STAFF'S LIST OF ISSUES |
7 | 5/7/2012 | PUC LEGAL | PL | COMMISSION STAFF'S FIRST RFI TO EL PASO ELECTRIC COMPANY QUESTIONS NO. KC-1-1 |
8 | 5/7/2012 | EL PASO ELECTRIC COMPANY | PL | LIST OF ISSUES |
9 | 5/8/2012 | PUC LEGAL | PL | SECOND RFI TO EL PASO ELECTRIC CO QUESTION NO. TH 2-1 |
25 | 5/29/2012 | CITY OF EL PASO | PL | REQUEST FOR HEARING |
44 | 6/20/2012 | PUC CADM | PL | SUPPLEMENTAL PRELIMINARY ORDER |
45 | 6/20/2012 | PUC CADM | PL | OUTGOING COMMISSION-SIGNED ORDER MAIL LOG |
47 | 6/25/2012 | EL PASO ELECTRIC COMPANY | PL | AGREED TWO WEEK DELAY IN SCHEDULE |
48 | 6/27/2012 | SOAH | PL | SOAH ORDER NO. 4: GRANTING REQUEST TO REVISE SCHEDULE |
50 | 6/29/2012 | EL PASO ELECTRIC COMPANY | PL | STATEMENT UNDER SECTION 4 OF PROTECTIVE ORDER DESIGNATING CONFIDENTIAL AND HIGHLY SENSITIVE PROTECTED MATERIALS |
49 | 6/28/2012 | EL PASO ELECTRIC COMPANY | RFI | RESPONSE TO CITY OF EL PASO'S 1ST RFI QUESTION NOS. CEP 1-1 TO CEP 1-5 |
46 | 6/22/2012 | EL PASO ELECTRIC COMPANY | RFI | RESPONSE TO COMMISSION STAFF'S 7TH RFI |
26 | 5/29/2012 | EL PASO ELECTRIC COMPANY | RFI | RESPONSE TO COMMISSION STAFF'S 4TH RFI |
10 | 5/9/2012 | PUC LEGAL | RFI | COMMISSION STAFF'S 3RD RFI TO EL PASO ELECTRIC COMPANY QUESTION NOS. KC-3-1 THROUGH KC-3-4 |
15 | 5/17/2012 | EL PASO ELECTRIC COMPANY | RFI | RESPONSE TO COMMISSION STAFF'S 1ST RFI |
17 | 5/18/2012 | PUC LEGAL | RFI | COMMISSION STAFF'S 4TH RFI TO EL PASO ELECTRIC CO. QUESTIONS NOS. 4-1- 4-10 |
18 | 5/21/2012 | EL PASO ELECTRIC COMPANY | RFI | Response to Staff 3rd RFI |
20 | 5/22/2012 | PUC LEGAL | RFI | COMMISSION STAFF'S 5TH RFI TO EL PASO ELECTRIC COMPANY QUESTION NO. TH 5-1 |
23 | 5/24/2012 | EL PASO ELECTRIC COMPANY | RFI | RESPONSE TO COMMISSION STAFF'S 2ND RFI |
24 | 5/24/2012 | PUC LEGAL | RFI | COMMISSION STAFF'S 6TH RFI TO EL PASO ELECTRIC COMPANY QUESTION NOS. STAFF 6 - 1 THROUGH STAFF 6 - 5 |
42 | 6/15/2012 | PUC LEGAL | RFI | COMMISSION STAFF'S 7TH RFI TO EL PASO ELECTRIC COMPANY QUESTION NOS. KC 7-1 THROUGH KC 7-2 |
43 | 6/18/2012 | CITY OF EL PASO | RFI | 1ST RFI TO EL PASO ELECTRIC CO; QUESTIONS NO. CEP 1-1 to CEP 1-5 |
34 | 6/1/2012 | EL PASO ELECTRIC COMPANY | RFI | SUPPLEMENTAL RESPONSE TO COMMISSION STAFF'S 4TH RFI |
35 | 6/1/2012 | EL PASO ELECTRIC COMPANY | RFI | RESPONSE TO COMMISSION STAFF'S 5TH RFI |
36 | 6/4/2012 | EL PASO ELECTRIC COMPANY | RFI | RESPONSE TO COMMISSION STAFF'S 6TH RFI |
27 | 5/30/2012 | CITY OF EL PASO | TEST | FILED IN ERROR - SEE DKT # 39973 ITEM # 78 |
Export to Excel |