Case Style   INVESTIGATION OF EMERGENCY PREPAREDNESS AND RESPONSE BY UTILITIES IN HOUSTON AND SURROUNDING COMMUNITIES

198 filing(s).

Item File Stamp Party Item Type Filing Description
1 7/15/2024 PUC COMPLIANCE & ENFORCEMENT PRJ CONTROL NUMBER REQUEST
2 7/15/2024 PUC EXECUTIVE DIRECTOR LTRS Memo opening investigation with Governor Abbott's letter attached
3 7/22/2024 PUC EXECUTIVE DIRECTOR LTRS Investigation scoping memo
4 7/24/2024 Mayor John Whitmire LTRS Hurricane Beryl Letter
5 7/25/2024 PUC EXECUTIVE DIRECTOR LTRS Response Letter Mayor Whitmire Hurricane Beryl Response
6 7/29/2024 PUC EXECUTIVE DIRECTOR LTRS Investigation documentation memo
7 7/29/2024 PUC INFRASTRUCTURE PRJ AEP Texas Inc. Vegetation Management Reports - 2013 to Present
8 7/29/2024 PUC INFRASTRUCTURE PRJ CenterPoint Energy Houston Electric, LLC Vegetation Management Reports - 2013 to Present
9 7/29/2024 PUC INFRASTRUCTURE PRJ Entergy Texas, Inc. Vegetation Management Reports - 2013 to Present
10 7/29/2024 PUC INFRASTRUCTURE PRJ Texas-New Mexico Power Company Vegetation Management Reports - 2013 to Present
11 7/29/2024 PUC INFRASTRUCTURE PRJ Electric Utility Distribution System Spending and Reliability Report - 2013 to 2022
12 7/30/2024 PUC INFRASTRUCTURE PRJ AEP Texas Inc. - Emergency Operations Plan
13 7/30/2024 PUC INFRASTRUCTURE PRJ CenterPoint Energy Houston Electric - Emergency Operations Plan
14 7/30/2024 PUC INFRASTRUCTURE PRJ Entergy Texas, Inc. - Emergency Operations Plan
15 7/30/2024 PUC INFRASTRUCTURE PRJ Texas-New Mexico Power Company - Emergency Operations Plan
16 7/31/2024 PUC INFRASTRUCTURE PRJ AEP Texas Inc. Storm Hardening Plan Summary - 2022 to Present
17 7/31/2024 PUC INFRASTRUCTURE PRJ CenterPoint Energy Houston Electric, LLC Storm Hardening Plan Summary - 2022 to Present
18 7/31/2024 PUC INFRASTRUCTURE PRJ Entergy Texas, Inc. Storm Hardening Plan Summary - 2020 to Present
19 7/31/2024 PUC INFRASTRUCTURE PRJ Texas-New Mexico Power Company Storm Hardening Plan Summary - 2020 to Present
20 7/31/2024 PUC CENTRAL RECORDS PL VOID. SEE ITEM 25.
21 7/31/2024 PUC CENTRAL RECORDS CONF VOID. SEE ITEM 25.
22 7/31/2024 PUC CENTRAL RECORDS CONF VOID. SEE ITEM 25.
23 7/31/2024 PUC CENTRAL RECORDS CONF VOID. SEE ITEM 25.
24 7/31/2024 PUC CENTRAL RECORDS CONF VOID. SEE ITEM 25.
25 8/1/2024 PUC CENTRAL RECORDS LTRS VOID MEMO
26 8/2/2024 PUC EXECUTIVE DIRECTOR LTRS CenterPoint Energy's response to Governor Abbott's July 16th letter
27 8/2/2024 PUC EXECUTIVE DIRECTOR RFI COMMISSION STAFF’S FIRST REQUEST FOR INFORMATION TO COMMUNITY CENTERS AND ORGANIZATIONS
28 8/2/2024 PUC EXECUTIVE DIRECTOR RFI COMMISSION STAFF’S FIRST REQUEST FOR INFORMATION TO LOCAL GOVERNMENTS
29 8/2/2024 PUC EXECUTIVE DIRECTOR RFI COMMISSION STAFF’S FIRST REQUEST FOR INFORMATION TO POWER GENERATION COMPANIES
30 8/2/2024 PUC EXECUTIVE DIRECTOR RFI COMMISSION STAFF’S FIRST REQUEST FOR INFORMATION TO TRADE ASSOCIATIONS
31 8/2/2024 PUC EXECUTIVE DIRECTOR RFI COMMISSION STAFF’S FIRST REQUEST FOR INFORMATION TO RETAIL ELECTRIC PROVIDERS
32 8/2/2024 PUC EXECUTIVE DIRECTOR RFI COMMISSION STAFF’S FIRST REQUEST FOR INFORMATION TO MEDICAL AND ELDERCARE FACILITIES
33 8/8/2024 City of Taylor Lake Village PRJ TLV response to Project 56822
34 8/12/2024 PUC COMPLIANCE & ENFORCEMENT RFI COMMISSION STAFF’S FIRST REQUEST FOR INFORMATION TO CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC
35 8/12/2024 PUC COMPLIANCE & ENFORCEMENT RFI COMMISSION STAFF’S FIRST REQUEST FOR INFORMATION TO AEP TEXAS, INC.
36 8/12/2024 PUC COMPLIANCE & ENFORCEMENT RFI COMMISSION STAFF’S FIRST REQUEST FOR INFORMATION TO TEXAS-NEW MEXICO POWER COMPANY
37 8/12/2024 PUC COMPLIANCE & ENFORCEMENT RFI COMMISSION STAFF’S FIRST REQUEST FOR INFORMATION TO ENTERGY TEXAS, INC.
38 8/12/2024 PUC COMPLIANCE & ENFORCEMENT RFI COMMISSION STAFF’S FIRST REQUEST FOR INFORMATION TO TARGETED ELECRIC COOPS
39 8/12/2024 PUC COMPLIANCE & ENFORCEMENT RFI COMMISSION STAFF’S FIRST REQUEST FOR INFORMATION TO TARGETED ELECTRIC MOUS
40 8/12/2024 PUC COMPLIANCE & ENFORCEMENT RFI COMMISSION STAFF’S FIRST REQUST FOR INFORMATION TO TARGETED WATER OR SEWER UTILITIES
41 8/12/2024 PUC COMPLIANCE & ENFORCEMENT RFI COMMISSION STAFF’S FIRST REQUST FOR INFORMATION TO TARGETED TELECOMMUNICATION UTILITIES
42 8/19/2024 PUC COMPLIANCE & ENFORCEMENT RFI Commission Staff's First Request for Information to Oncor Electric Delivery Company, LLC
43 8/26/2024 CITY OF JASPER PRJ City of Jasper PUCT First Request Investigation after Hurricane Beryl
44 8/26/2024 WOODLAND HILLS WATER , LLC RFI Responses to PUC 1st RFI
45 8/27/2024 CITY OF LIVINGSTON PRJ City of Livingston PUCT First Request Investigation after Hurricane Beryl
46 8/27/2024 CITY OF LIVINGSTON PRJ City of Livingston PUCT First Request Investigation after Hurricane Beryl Amended 8-27-24
47 8/27/2024 City of College Station PRJ College Station's Project 56822 Filing
48 8/27/2024 CITY OF BRENHAM RFI PUCT RFI - MOU Response
49 8/27/2024 CITY OF BRENHAM CONF VOID SEE ITEM 169
50 8/27/2024 CITY OF CUERO RFI PUCT RFI - MOU Response
51 8/27/2024 CITY OF FLATONIA RFI PUCT RFI - MOU Response
52 8/27/2024 CITY OF GIDDINGS RFI PUCT RFI - MOU Response
53 8/27/2024 CITY OF LA GRANGE RFI PUCT RFI - MOU Response
54 8/27/2024 CITY OF LEXINGTON PRJ PUCT RFI - MOU Response
55 8/27/2024 CITY OF MOULTON RFI PUCT RFI - MOU Response
56 8/27/2024 CITY OF SCHULENBURG PRJ PUCT RFI - MOU Response
57 8/27/2024 CITY OF SHINER RFI PUCT RFI - MOU Response
58 8/27/2024 CITY OF WEIMAR RFI PUCT RFI - MOU Response
59 8/28/2024 CITY OF HILLSHIRE VILLAGE RFI City of Hillshire Village's Response to Commission Staff's First Request for Information
60 8/28/2024 CITY OF TIMPSON PRJ PUCT RFI - MOU Response
61 8/28/2024 NAVARRO COUNTY ELECTRIC COOPERATIVE, INC. RFI Response to commission staff first request for information to targeted electric cooperatives
62 8/28/2024 Karnes Electric Cooperative, Inc. PL Karnes Electric Cooperative's Response to Commission Staff's First Request for Information to Karnes Electric Cooperative Question Nos. Staff 1-1 Through 1-120
63 8/28/2024 CITY OF HALLETTSVILLE PRJ Responses to Docket / Project Number 56822 and MESA agreement and Mutual Aid agreement with the county that are referenced in our responses
64 8/29/2024 MSEC ENTERPRISES, INC. RFI MSEC Enterprises, Inc and MSEC Wastewater, Inc.'s Response to Commission Staff's First Request for Information
65 8/29/2024 WHARTON COUNTY ELECTRIC COOPERATIVE, INC. PRJ PUCT RFI - Co-op Response
66 8/29/2024 WHARTON COUNTY ELECTRIC COOPERATIVE, INC. PRJ PUCT RFI - Co-op Response Part 2
67 8/29/2024 CIty of Caldwell RFI City of Caldwell's First Request for Information to Targeted Electric MOUS
68 8/29/2024 Bartlett Electric Cooperative RFI PUCT RFI response Project No. 56822
69 8/29/2024 Heart of Texas Electric Cooperative, Inc. RFI Heart of Texas Electric Cooperative's Response to Commission Staff's First Request for Information
70 8/29/2024 MEDINA ELECTRIC COOPERATIVE, INC. PRJ MEDINA ELECTRIC COOPERATIVE’S RESPONSE TO COMMISSION STAFF’S FIRST REQUEST FOR INFORMATION TO TARGETED ELECTRIC CO-OPS QUESTION NOS. STAFF 1-1 THROUGH 1-120
71 8/29/2024 HOUSTON COUNTY ELECTRIC COOPERATIVE, INC. RFI Houston County Electric Cooperative's Response to Staff's First Request for Information
72 8/29/2024 WHARTON COUNTY ELECTRIC COOPERATIVE, INC. PRJ PUCT RFI - Co-op Response Part 3
73 8/29/2024 ENGIE RESOURCES LLC PRJ Responses to Investigation of Emergency Preparedness by Utilities in Houston and Surrounding Communities
74 8/29/2024 HEN INFRASTRUCTURE, L.L.C. RFI HEN Infrastructure, LLC Response to Commission Staff's Request for Information
75 8/29/2024 SAN PATRICIO ELECTRIC COOPERATIVE INC PRJ PUCT RFI - Co-op Response
76 8/29/2024 CITY OF YOAKUM PRJ PUCT RFI - MOU Response
77 8/29/2024 Texas Assisted Living Association RFI TALAComments_PUC_HurricaneBeryl_RFI
78 8/30/2024 LAMAR COUNTY ELECTRIC COOPERATIVE, INC. RFI PUCT Project #56822 Responses to First Request for Information
79 8/30/2024 BRYAN TEXAS UTILITIES RFI Bryan Texas Utilities Response to Staff First RFIs
80 8/30/2024 BRYAN TEXAS UTILITIES CONF BTU's Confidential Attachments to Staff 1-11, 1-12, and 1-13
81 8/30/2024 Piney Point Village PRJ PROJECT NO. 56822 COMMISSION STAFF'S FIRST REQUEST FOR INFORMATION TO LOCAL GOVERNMENTS QUESTION NOS. LG 1-1 THROUGH 1-19
82 8/30/2024 VICTORIA ELECTRIC COOPERATIVE, INC. PRJ PUCT RFI - Co-op Response
83 8/30/2024 CITY OF BELLVILLE PRJ PUCT RFI - MOU Response
84 8/30/2024 NEXTERA WATER TEXAS, LLC RFI NextEra Water Texas, LLC's Response to Commission Staff's First Request for Information.
85 8/30/2024 PANOLA-HARRISON ELECTRIC COOPERATIVE, INC. RFI Panola-Harrison Electric Cooperative, Inc.'s Response to Staff's First Request for Information
86 8/30/2024 NEXTERA WATER TEXAS, LLC CONF NextEra Water Texas, LLC's CONFIDENTIAL Exhibit Attachments in Response to Commission Staff's First Request for Information.
87 8/30/2024 CITY OF ROBSTOWN PRJ PUCT RFI - MOU Response
88 8/30/2024 FAYETTE ELECTRIC COOPERATIVE, INC PRJ PUCT RFI - Co-op Response
89 8/30/2024 MID-SOUTH ELECTRIC COOPERATIVE ASSOCIATION RFI MidSouth Electric Cooperative's Response to Staff's First Request for Information
90 8/30/2024 TRINITY VALLEY ELECTRIC COOPERATIVE INC. RFI TVEC's Responses to Staff's First RFIs
91 8/30/2024 TRINITY VALLEY ELECTRIC COOPERATIVE INC. CONF TVEC's Confidential Attachment to Staff 1-30
92 8/30/2024 SAN BERNARD ELECTRIC COOPERATIVE, INC PRJ San Bernard Electric Cooperative's Response To Commission Staff's First Request for Information.
93 8/30/2024 Sam Houston Electric Cooperative, Inc. RFI Sam Houston Electric Cooperative's Responses to Staff's First RFI
94 8/30/2024 SAM HOUSTON ELECTRIC COOPERATIVE, INC CONF SHEC's Confidential Attachments to Staff 1-12, 1-43, 1-76, and 1-94
95 8/30/2024 NRG ENERGY, INC. PRJ NRG Energy, Inc.'s Response to Commission Staff's First Request for Information to Power Generation Companies
96 8/30/2024 CSWR TEXAS UTILITY OPERATING COMPANY, LLC PL 56822 CSWR-Texas Response to Staff 1st RFI
97 8/30/2024 AEP TEXAS INC. RFI AEP TEXAS INC. RESPONSE TO COMMISSION STAFF'S FIRST REQUEST FOR INFORMATION.
98 8/30/2024 CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC RFI CenterPoint Energy Houston Electric, LLC’s Response to the Public Utility Commission of Texas First Requests for Information
99 8/30/2024 BLUEBONNET ELECTRIC COOPERATIVE, INC. MISC BBEC Response to Staff's 1st RFI PUBLIC
100 8/30/2024 BLUEBONNET ELECTRIC COOPERATIVE, INC. CONF CONFIDENTIAL PAGES TO BBEC Response to Staff's 1st RFI
101 8/30/2024 Texas Restaurant Association PRJ Response to Project No. 56822 from the Texas Restaurant Association
102 8/30/2024 GUADALUPE VALLEY ELECTRIC COOPERATIVE, INC MISC GVEC Response to Staff's 1st RFIs PUBLIC
103 8/30/2024 GUADALUPE VALLEY ELECTRIC COOPERATIVE, INC CONF CONFIDENTIAL PAGES FROM GVEC Response to Staff's 1st RFIs
104 8/30/2024 CHAMPION ENERGY SERVICES LLC CONF Champion Energy Services, LLC and Calpine Energy Solutions, LLC's Confidential Responses to PUCT RFI re Customer Outages During Beryl and May 2024 Derecho
105 8/30/2024 Texas Water Utilities, L.P. and Corix Utilities (Texas) Inc. RFI Response to Staff’s First RFI to Water Utilities
106 8/30/2024 AEP TEXAS INC. CONF HIGHLY SENSITIVE RESPONSES TO COMMISSION STAFF'S FIRST REQUEST FOR INFORMATION
107 8/30/2024 ALLIANCE FOR RETAIL MARKETS MISC Alliance for Retail Markets' Response to Commission Staff's First Request for Information to Retail Electric Providers
108 8/30/2024 City of Friendswood RFI Response to RFI
109 8/30/2024 CITY OF SAN AUGUSTINE PRJ PUCT RFI - MOU Response
110 8/30/2024 CHEROKEE COUNTY ELECTRIC COOPERATIVE ASSOCIATION RFI Cherokee County Electric Cooperative Association's Response to Staff's First Request for Information
111 8/30/2024 NRG Energy, Inc. Family of REPs RFI Response to Commission Staff's First Requests for Information of the NRG Energy, Inc. Family of REPs
112 8/30/2024 AT&T RFI AT&T’s Response to Commission Staff’s First Request for Information
113 8/30/2024 ENTERGY TEXAS, INC. RFI ETI's Responses to Staff's 1st RFI_Questions 1 Through 55
114 8/30/2024 Texas Water Utilities, L.P. and Corix Utilities (Texas) Inc. CONF Attachment Staff 1-7b
115 8/30/2024 AT&T CONF AT&T’s Response to Commission Staff’s First Request for Information
116 8/30/2024 ENTERGY TEXAS, INC. CONF ETI's HSPM Responses to Staff's First RFI_Att. 12 & 43
117 8/30/2024 VISTRA CORP. PRJ Vistra PGCs Response to DICE RFIs Emergency Preparedness Utilities
118 8/30/2024 Texas Water Utilities, L.P. and Corix Utilities (Texas) Inc. CONF Attachment Staff 1-7a (Part 1)
119 8/30/2024 VISTRA CORP. PRJ Vistra REP Retail RFI Responses to DICE Emergency Preparedness Utilities
120 8/30/2024 CITY OF HOUSTON RFI City of Houston response to Commission staff's first request for information to local governments, for Project Number 56822.
121 8/30/2024 Texas Water Utilities, L.P. and Corix Utilities (Texas) Inc. CONF 56822 CONF Attachment Staff 1-7a Parts 2-3
122 8/30/2024 Texas Water Utilities, L.P. and Corix Utilities (Texas) Inc. CONF Attachment Staff 1-7b - Part 4
123 8/30/2024 NAVASOTA VALLEY ELECTRIC CO-OP PRJ Navasota Valley Electric Cooperative, Inc.'s Response to Commission Staff's First Request for Information to Targeted Electric Co-ops
124 8/30/2024 MAGIC VALLEY ELECTRIC COOPERATIVE, INC. PRJ PUCT RFI - Co-op Response
125 8/30/2024 CITY OF KIRBYVILLE PRJ VOID: SEE ITEM 176
126 8/30/2024 NUECES ELECTRIC COOPERATIVE, INC. PRJ Project 56822- Nueces Electric Cooperative, Inc.- RFI Response
127 8/30/2024 TEXAS ENERGY ASSOCIATION FOR MARKETERS RFI Response to 1st RFI to Trade Assn.
128 8/30/2024 QUADVEST LP PL VOID SEE ITEM 132
129 8/30/2024 Aggregated REP Group RFI Response to 1st RFI to REPS
130 8/30/2024 RIO GRANDE ELECTRIC COOPERATIVE INC. PRJ PUCT RFI - Co-op Response
131 8/30/2024 QUADVEST LP PL Quadvest LP's Response to Staff's 1st RFIs to Utilities
132 8/30/2024 QUADVEST LP PL Letter regarding filing error
133 8/30/2024 QUADVEST LP CONF Confidential Exhibit D to Quadvest Response to Staff 1st RFIs
134 8/30/2024 JACKSON ELECTRIC COOPERATIVE, INC. PRJ PUCT RFI - Co-op Response
135 8/30/2024 TEXAS-NEW MEXICO POWER COMPANY RFI Texas-New Mexico Power Company’s Responses to Staff’s First Request for Information
136 8/30/2024 ENTERGY TEXAS, INC. RFI ETI's Responses to Staff's First RFI_Questions 56 Through 120
137 8/30/2024 AQUA TEXAS RFI 56822 Aqua Texas Response to Staff 1st RFI
138 8/30/2024 CITY OF HEMPSTEAD PRJ PUCT RFI - MOU Response
139 9/3/2024 TEXAS-NEW MEXICO POWER COMPANY CONF Texas-New Mexico Power Company’s Confidential Attachments in Response to Staff’s First Request for Information
140 9/3/2024 ENTERGY TEXAS, INC. CONF ETI's HSPM Responses to Staff's First RFI_66, 72, 76 and 86
141 9/3/2024 AQUA TEXAS CONF 56822 Aqua Texas CONFIDENTIAL Attachment to Response to Staff 1st RFI
142 9/3/2024 CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC CONF CenterPoint Energy Houston Electric, LLC’s Response to the Public Utility Commission of Texas First Requests for Information - CONFIDENTIAL
143 9/4/2024 RUSK COUNTY ELECTRIC COOPERATIVE, INC. PRJ VOID SEE ITEM 159
144 9/4/2024 WOOD COUNTY ELECTRIC COOPERATIVE, INC. RFI Wood County Electric Cooperative, Inc.'s Response to Staff's First Request for Information
145 9/4/2024 JASPER NEWTON ELECTRIC COOPERATIVE, INC. RFI Jasper-Newton Electric Cooperative, Inc.'s Response to Staff's First Request for Information
146 9/4/2024 BOWIE-CASS ELECTRIC COOPERATIVE, INC. PRJ BCEC responses to Project 56822 RFI's for Hurricane Beryl.
147 9/4/2024 UNDINE DEVELOPMENT, LLC RFI VOID SEE ITEM 149
148 9/5/2024 UNDINE DEVELOPMENT LLC CONF VOID SEE ITEM 149
149 9/5/2024 UNDINE, LLC LTRS Undine, LLC Letter to Central Records to Void Item Nos. 147 and 148
150 9/5/2024 Undine, LLC RFI Undine, LLC's Response to Staff's First Request for Information
151 9/5/2024 Undine, LLC CONF CONFIDENTIAL Attachment Staff 1-4 - Undine Electric Accounts and System Addresses CONFIDENTIAL Attachment Staff 1-7(a) CONFIDENTIAL Attachment Staff 1-7(b) - H2O Innovation Inc.'s (H2O Innovation) Hurricane Preparedness Plan
152 9/5/2024 DEEP EAST TEXAS ELECTRIC COOPERATIVE INC. RFI Deep East Texas Electric Cooperative, Inc.'s Response to Staff's First Request for Information
153 9/5/2024 PUC EXECUTIVE DIRECTOR PRJ Investigation Status Update Memo
154 9/6/2024 CITY OF LIBERTY PRJ City of Liberty PUCT First Request Investigation after Hurricane Beryl
155 9/6/2024 CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC RFI CenterPoint Energy Houston Electric, LLC Response to Public Utility Commission of Texas Request for Information 1-97
156 9/6/2024 CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC RFI Attached roadmap to responses filed on August 30, 2024, to the Requests for Information issued by Staff
157 9/6/2024 UPSHUR RURAL ELECTRIC COOPERATIVE CORPORATION REG URECC Response to Staff's 1st RFIs PUBLIC
158 9/6/2024 UPSHUR RURAL ELECTRIC COOPERATIVE CORPORATION CONF CONFIDENTIAL PAGES FROM URECC Response to Staff's 1st RFIs
159 9/6/2024 RUSK COUNTY ELECTRIC COOPERATIVE, INC. CONF Rusk County Electric Cooperative, Inc Response to Project 56822
160 9/6/2024 ONCOR ELECTRIC DELIVERY COMPANY LLC RFI RESPONSE OF ONCOR ELECTRIC DELIVERY COMPANY LLC TO COMMISSION STAFF'S FIRST REQUEST FOR INFORMATION
161 9/6/2024 ONCOR ELECTRIC DELIVERY COMPANY LLC CONF CONFIDENTIAL ONCOR'S RESPONSE TO STAFF RFI SET NO. 1, QUESTION NO. 1-79
162 9/6/2024 ONCOR ELECTRIC DELIVERY COMPANY LLC CONF CONFIDENTIAL ONCOR'S RESPONSE TO STAFF RFI SET NO. 1, QUESTION NO. 1-105
163 9/6/2024 ONCOR ELECTRIC DELIVERY COMPANY LLC CONF CONFIDENTIAL ONCOR'S RESPONSE TO STAFF RFI SET NO. 1, QUESTION NO. 1-107
164 9/6/2024 BROWNSVILLE PUBLIC UTILITIES BOARD RFI Brownsville Public Utilities Board Project No. 56822 RFI.pdf
165 9/6/2024 TEXAS-NEW MEXICO POWER COMPANY RFI Texas-New Mexico Power Company’s Supplemental Responses to Commission Staff’s First Request for Information
166 9/9/2024 TEXAS-NEW MEXICO POWER COMPANY CONF Texas-New Mexico Power Company’s Supplemental Documents in Response to Staff 1-23
167 9/9/2024 CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC CONF CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC CONFIDENTIAL RESPONSE TO REQUEST FOR INFORMATION 1-97
168 9/16/2024 CITY OF NEWTON RFI responses to Staff's Targeted MOU RFIs
169 9/16/2024 CITY OF BRENHAM PRJ VOID: SEE ITEM 175
170 9/17/2024 CHAMPION ENERGY SERVICES LLC MISC Champion and Solutions' Responses to PUCT RFIs re Hurricane Beryl and Derecho
171 9/17/2024 CITY OF HEMPHILL COM The City of Hemphill's answers to the "RFIs to Electric MOUs" document concerning Hurricane Beryl.
172 9/18/2024 TEXAS-NEW MEXICO POWER CO MISC Texas-New Mexico Power Company’s Supplemental Responses to Commission Staff’s First Request for Information
173 9/19/2024 CITY OF BRENHAM PRJ PUCT RFI - MOU Response
174 9/19/2024 CITY OF BRENHAM CONF PUCT RFI - MOU Response
175 9/19/2024 CITY OF BRENHAM PRJ PUCT RFI - MOU Response
176 9/20/2024 CITY OF KIRBYVILLE PRJ PUCT RFI - MOU Response
177 9/20/2024 CENTERPOINT ENERGY HOUSTON ELECTRIC PL CenterPoint Energy Houston Electric, LLC Confidentiality Statement and Redacted Documents
178 9/23/2024 Astound Broadband PRJ Astound Broadband's Response to Staff's First Request for Information
179 9/23/2024 ENTERGY TEXAS, INC. LTRS ETI's Letter Regarding Commission Staff's First RFI
180 9/24/2024 UTILITIES INVESTMENT CO., INC. CONF PUCT RFI Response
181 9/24/2024 LIBERTY COUNTY UTILITIES, LLC CONF PUCT RFI Response
182 9/24/2024 JOHNSTON WATER UTILITY LLC CONF PUCT RFI Response
183 9/24/2024 SOUTHWEST ARKANSAS ELECTRIC COOPERATIVE CORP. RFI Southwest Arkansas Electric Cooperative Corporation's Responses To Commission Staff's First Request for Information To Targeted Electric Coops Question Nos. Staff 1-1 through 1-120
184 9/24/2024 T& W WATER SERVICE dba BLUE TOPAZ UTILITIES CONF PROJECT 56822 - INVESTIGATION OF EMERGENCY PREPAREDNESS AND RESPONSE
185 9/25/2024 UTILITIES INVESTMENT CO., INC. DBA RANCH CREST WATER COMPANY CONF PUCT RFI Response
186 9/25/2024 Spectrum RFI Response to Commission Staff’s First Request for Information
187 9/25/2024 Spectrum CONF Confidential Attachments to Response to Commission Staff’s First Request for Information
188 9/25/2024 Nextlink Internet MISC Nextlink Internet Response To First RFI to Targeted Telecommunications Utilities
189 9/26/2024 AEP TEXAS INC. RFI SUPPLEMENTAL RESPONSE TO COMMISSION STAFFS’ 1-76 AND 1-86
190 9/27/2024 UNDINE, LLC RFI Undine, LLC's Supplemental Response to Staff's First Request for Information
191 9/27/2024 ENCHANTED ROCK, LLC PRJ Enchanted Rock, LLC's Response to Commission Staff's First Request for Information to Power Generation Companies
192 10/3/2024 CENTERPOINT ENERGY HOUSTON ELECTRIC PRJ CenterPoint Energy Houston Electric PUCT Presentation
193 10/4/2024 MG Spoor Consulting LLC. and GridSky Strategies Inc. PRJ MG Spoor Consulting and GridSky Strategies PUC workshop presentation
194 10/4/2024 PUC EXECUTIVE DIRECTOR PRJ Sequence of events for October 5, 2024 workshop
195 10/15/2024 CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC RFI CenterPoint Energy Houston Electric, LLC’s Response to the Public Utility Commission of Texas First Request for Information, PUC-RFI01-128S Supplemental
196 10/25/2024 CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC RFI CenterPoint Energy Houston Electric, LLC’s Response to the Public Utility Commission of Texas First Request for Information, PUC-RFI01-019S Supplemental
197 11/19/2024 PUC EXECUTIVE DIRECTOR PRJ Investigation Report Draft and Memo
198 11/21/2024 PUC EXECUTIVE DIRECTOR PRJ Final Report
Export to Excel