Case Style   PUC PROCEEDING TO MODIFY REQUIREMENTS FOR CERTIFICATE OF CONVENIENCE AND NECESSITY FOR SERVICE AREA BOUNDARY AND TRANSMISSION CONSTRUCTION REPORTS

37 filing(s).

Item File Stamp Party Filing Description
1 6/27/2012 PUC INFRASTRUCTURE AND RELIABILITY CONTROL NUMBER REQUEST FORM: PUC PROCEEDING TO MODIFY REQUIREMENTS FOR CERTIFICATE OF CONVENIENCE AND NECESSITY FOR A PROPOSED TRANSMISSION LINE AND SERVICE AREA BOUNDARY, AND TRANSMISSION CONSTRUCTION REPORTS REVISED 1/24/2013 - PUC PROCEEDING TO MODIFY REQUIREMENTS FOR CERTIFICATE OF CONVENIENCE AND NECESSITY FOR SERVICE AREA BOUNDARY AND TRANSMISSION CONSTRUCTION REPORTS
2 8/10/2012 PUC INFRASTRUCTURE AND RELIABILITY Project to adjust applications and forms so that the Commission will collect proposed and constructed transmission line mapping data in GIS.
3 8/20/2012 PUC CADM REQUEST FOR COMMENTS ON APPLICATION AND FORM CHANGES
4 8/21/2012 PUC CADM ACKNOWLEDGEMENT OF RECEIPT FILE NAME 0820C.052
5 9/5/2012 CENTERPOINT ENERGY REQUEST FOR WORKSHOP
6 9/11/2012 PUC Infrastructure and Reliability PUBLIC NOTICE OF CHANGE IN COMMENT DEADLINES AND NOTICE OF WORKSHOP
7 9/21/2012 TEXAS ELECTRIC COOPERATIVES, INC. LIST OF ISSUES
8 9/21/2012 ONCOR ELECTRIC DELIVERY COMPANY LLC PROPOSED QUESTIONS
9 9/21/2012 SOUTHWESTERN PUBLIC SERVICE COMPANY RESPONSE TO REQUEST FOR QUESTIONS AND ISSUES
10 9/21/2012 BRAZOS ELECTRIC POWER COOPERATIVE INC RESPONSE TO REQUEST FOR QUESTIONS AND ISSUES
11 9/21/2012 ENTERGY TEXAS INC QUESTION/ISSUES TO BE ADDRESSED
12 9/21/2012 CITY OF AUSTIN QUESTIONS IN RESPONSE TO THE COMMISSION'S NOTICE OF CHANGE IN COMMENTS DEADLINES AND NOTICE OF WORKSHOP
13 9/21/2012 CENTERPOINT ENERGY HOUSTON ELECTRIC LLC QUESTIONS AND ISSUES FOR THE WORKSHOP
14 9/21/2012 SHARYLAND UTLITIES LP FILING OF QUESTIONS TO BE ADDRESSED AT WORKSHOP
15 9/21/2012 AEP TEXAS CENTRAL ET AL LIST OF QUESTIONS
16 9/21/2012 LCRA TRANSMISSION SERVICES CORPORATION SUGGESTED QUESTIONS AND ISSUES
17 10/4/2012 CENTERPOINT ENERGY HOUSTON ELECTRIC LLC WITHDRAWAL OF REQUEST FOR WORKSHOP
18 10/5/2012 PUC INFRASTRUCTURE AND RELIABILITY CCN applications and transmission construction reports
19 10/16/2012 PUC Infrastructure and Reliability Notice of Second Comment Deadline Extension
20 10/25/2012 PUC Infrastructure and Reliability CCN Appllications and Monthly Construction Progress Report Form changes
21 2/7/2013 PUC INFRASTRUCTURE AND RELIABILITY OPEN MEETING FEBRUARY 14, 2013; AGENDA ITEM NO. 7; Proceeding to Modify Requirements for Certificate of Convenience and Necessity for a Service Area Boundary and Transmission Construction Reports
22 2/14/2013 PUC CADM NOTICE OF PROPOSED REVISIONS TO FORMS
23 2/19/2013 PUC CADM NOTICE OF PROPOSED REVISIONS TO FORM
24 3/21/2013 ONCOR ELECTRIC DELIVERY COMPANY LLC INITIAL COMMENTS
25 3/22/2013 LONE STAR TRANSMISSION LLC INITIAL COMMENTS
26 3/22/2013 CENTERPOINT ENERGY COMMENTS
27 3/22/2013 TEXAS-NEW MEXICO POWER COMPANY INITIAL COMMENTS
28 3/22/2013 EAST TEXAS ELECTRIC COOPERATIVE INC COMMENTS
29 3/22/2013 AEP COMPANIES COMMENTS
30 3/22/2013 CITY OF AUSTIN DBA AUSTIN ENERGY COMMENTS
31 3/22/2013 ENTERGY TEXAS INC INITIAL COMMENTS
32 3/22/2013 SOUTHWESTERN PUBLIC SERVICE CO. (SPS) COMMENTS
33 3/22/2013 LCRA TSC INITIAL COMMENTS
34 3/26/2013 LCRA TRANSMISSION SERVICES CORPORATION CORRECTED COMMENTS
35 3/29/2013 SOUTHWESTERN PUBLIC SERVICE CO. (SPS) REPLY COMMENTS
36 6/26/2013 PUC OVERSIGHT & ENFORCEMENT OPEN MEETING JULY 3, 2013; AGENDA ITEM NO. 6; PROPOSAL FOR ADOPTION
37 7/8/2013 PUC CADM ORDER ADOPTING APPLICATION FORM FOR A CERTIFICATE OF CONVENIENCE AND NECESSITY FOR A SERVICE AREA BOUNDARY AND INSTRUCTIONS FOR THE MONTHLY CONSTRUCTION PROGRESS REPORT FORM AS APPROVED AT THE JULY 3, 2013 OPEN MEETING