Filings for 40343



Case Style   APPLICATION OF EL PASO ELECTRIC COMPANY FOR APPROVAL TO REVISE ITS ENERGY EFFICIENCY COST RECOVERY FACTOR AND REQUEST TO ESTABLISH REVISED GOALS AND COST CAPS

63 filing(s).

Item File Stamp Party Filing Description
1 4/26/2012 EL PASO ELECTRIC COMPANY REQUEST FOR ASSIGNMENT OF DOCKET NUMBER RE: APPLICATION OF EL PASO ELECTRIC COMPANY FOR APPROVAL TO REVISE ITS ENERGY EFFICIENCY COST RECOVERY FACTOR AND REQUEST TO ESTABLISH REVISED GOALS AND COST CAPS
2 4/30/2012 EL PASO ELECTRIC COMPANY APPLICATION OF EL PASO ELECTRIC COMPANY FOR APPROVAL TO REVISE ITS ENERGY EFFICIENCY COST RECOVERY FACTOR AND REQUEST TO ESTABLISH REVISED GOALS AND COST CAPS
3 4/30/2012 PUC CADM ORDER OF REFERRAL
4 5/2/2012 SOAH SOAH ORDER NO. 1: SETTING OUT PROCEDURAL SCHEDULE AND NOTICE OF PREHEARING CONFERENCE
5 5/3/2012 EL PASO ELECTRIC COMPANY CHANGE OF IT'S PROPOSED MANNER OF GIVING NOTICE
6 5/7/2012 PUC LEGAL COMMISSION STAFF'S LIST OF ISSUES
7 5/7/2012 PUC LEGAL COMMISSION STAFF'S FIRST RFI TO EL PASO ELECTRIC COMPANY QUESTIONS NO. KC-1-1
8 5/7/2012 EL PASO ELECTRIC COMPANY LIST OF ISSUES
9 5/8/2012 PUC LEGAL SECOND RFI TO EL PASO ELECTRIC CO QUESTION NO. TH 2-1
10 5/9/2012 PUC LEGAL COMMISSION STAFF'S 3RD RFI TO EL PASO ELECTRIC COMPANY QUESTION NOS. KC-3-1 THROUGH KC-3-4
11 5/10/2012 PUC CADM ORDER REQUESTING BRIEFING ON THRESHOLD LEGAL/ POLICY ISSUES
12 5/11/2012 PUC CADM OPEN MEETING, MAY 18, 2012; AGENDA ITEM No. 6; DRAFT PRELIMINARY ORDER
13 5/11/2012 EL PASO ELECTRIC COMPANY PROOF OF NOTICE
14 5/16/2012 PUC CADM Revised Draft Preliminary Order
15 5/17/2012 EL PASO ELECTRIC COMPANY RESPONSE TO COMMISSION STAFF'S 1ST RFI
16 5/18/2012 CITY OF EL PASO MOTION TO INTERVENE
17 5/18/2012 PUC LEGAL COMMISSION STAFF'S 4TH RFI TO EL PASO ELECTRIC CO. QUESTIONS NOS. 4-1- 4-10
18 5/21/2012 EL PASO ELECTRIC COMPANY Response to Staff 3rd RFI
19 5/21/2012 EL PASO ELECTRIC COMPANY CONFIDENTIAL- RESPONSE TO STAFF KC 3-3, ATTACHMENT 1; BATE STAMP: 1-4
20 5/22/2012 PUC LEGAL COMMISSION STAFF'S 5TH RFI TO EL PASO ELECTRIC COMPANY QUESTION NO. TH 5-1
21 5/22/2012 PUC CADM Preliminary Order
22 5/22/2012 PUC CADM OUTGOING COMMISSION - SIGNED ORDER MAIL LOG
23 5/24/2012 EL PASO ELECTRIC COMPANY RESPONSE TO COMMISSION STAFF'S 2ND RFI
24 5/24/2012 PUC LEGAL COMMISSION STAFF'S 6TH RFI TO EL PASO ELECTRIC COMPANY QUESTION NOS. STAFF 6 - 1 THROUGH STAFF 6 - 5
25 5/29/2012 CITY OF EL PASO REQUEST FOR HEARING
26 5/29/2012 EL PASO ELECTRIC COMPANY RESPONSE TO COMMISSION STAFF'S 4TH RFI
27 5/30/2012 CITY OF EL PASO FILED IN ERROR - SEE DKT # 39973 ITEM # 78
28 5/30/2012 CITY OF EL PASO BRIEF ON THRESHOLD LEGAL/ POLICY ISSUES
29 5/30/2012 EL PASO ELECTRIC COMPANY RESPONSE TO ORDER REQUESTING BRIEFING ON THRESHOLD LEGAL/ POLICY ISSUES
30 5/30/2012 PUC LEGAL STAFF'S BRIEF ON THRESHOLD LEGAL/POLICY ISSUES
31 5/30/2012 TEXAS INDUSTRIAL ENERGY CONSUMERS MOTION TO INTERVENE
32 5/30/2012 SIERRA CLUB, LONE STAR CHAPTER COMMENTS
33 5/31/2012 PUC LEGAL COMMISSION STAFF'S PROPOSED PROCEDURAL SCHEDULE
34 6/1/2012 EL PASO ELECTRIC COMPANY SUPPLEMENTAL RESPONSE TO COMMISSION STAFF'S 4TH RFI
35 6/1/2012 EL PASO ELECTRIC COMPANY RESPONSE TO COMMISSION STAFF'S 5TH RFI
36 6/4/2012 EL PASO ELECTRIC COMPANY RESPONSE TO COMMISSION STAFF'S 6TH RFI
37 6/4/2012 EL PASO ELECTRIC COMPANY CONFIDENTIAL - RESPONSE TO STAFF 6-1 ATTACHMENT 1 : BATE STAMP : 1 CD
38 6/4/2012 EL PASO ELECTRIC COMPANY STATEMENT UNDER SECTION 4 OF PROTECTIVE ORDER DESIGNATING CONFIDENTIAL AND HIGHLY SENSITIVE PROTECTED MATERIALS
39 6/5/2012 SOAH SOAH ORDER NO. 3 : PROTECTIVE ORDER
40 6/6/2012 SOAH SOAH ORDER NO. 2 : MEMORIALIZING PREHEARING CONFERENCE, GRANTING MOTIONS TO INTERVENE, REVISING PROCEDURAL SCHEDULE, AND NOTICE OF HEARING
41 6/6/2012 EL PASO ELECTRIC COMPANY STATEMENT UNDER SECTION 4 OF PROTECTIVE ORDER DESIGNATING CONFIDENTIAL AND HIGHLY SENSITIVE PROTECTED MATERIALS
42 6/15/2012 PUC LEGAL COMMISSION STAFF'S 7TH RFI TO EL PASO ELECTRIC COMPANY QUESTION NOS. KC 7-1 THROUGH KC 7-2
43 6/18/2012 CITY OF EL PASO 1ST RFI TO EL PASO ELECTRIC CO; QUESTIONS NO. CEP 1-1 to CEP 1-5
44 6/20/2012 PUC CADM SUPPLEMENTAL PRELIMINARY ORDER
45 6/20/2012 PUC CADM OUTGOING COMMISSION-SIGNED ORDER MAIL LOG
46 6/22/2012 EL PASO ELECTRIC COMPANY RESPONSE TO COMMISSION STAFF'S 7TH RFI
47 6/25/2012 EL PASO ELECTRIC COMPANY AGREED TWO WEEK DELAY IN SCHEDULE
48 6/27/2012 SOAH SOAH ORDER NO. 4: GRANTING REQUEST TO REVISE SCHEDULE
49 6/28/2012 EL PASO ELECTRIC COMPANY RESPONSE TO CITY OF EL PASO'S 1ST RFI QUESTION NOS. CEP 1-1 TO CEP 1-5
50 6/29/2012 EL PASO ELECTRIC COMPANY STATEMENT UNDER SECTION 4 OF PROTECTIVE ORDER DESIGNATING CONFIDENTIAL AND HIGHLY SENSITIVE PROTECTED MATERIALS
51 7/11/2012 EL PASO ELECTRIC COMPANY AGREED ADDITIONAL TWO WEEK DELAY IN SCHEDULE
52 7/17/2012 SOAH SOAH ORDER NO 5 GRANTING REQUEST TO REVISE SCHEDULE
53 7/25/2012 EL PASO ELECTRIC COMPANY NOTIFICATION OF ORAL AGREEMENT
54 8/8/2012 EL PASO ELECTRIC COMPANY Stipulation and Settlement Agreement
55 8/8/2012 EL PASO ELECTRIC COMPANY JOINT MOTION TO ADMIT EVIDENCE AND REMAND TO THE COMMISSION
56 8/10/2012 SOAH SOAH ORDER NO 6 GRANTING JOINT MOTION TO ADMIT EVIDENCE AND REMAND TO THE COMMISSION, CANCELLING HEARING
57 8/13/2012 PUC CADM PROPOSED ORDER
58 9/4/2012 EL PASO ELECTRIC COMPANY CORRECTION TO PROPOSED ORDER
59 9/6/2012 PUC CADM REVISED PROPOSED ORDER
60 9/12/2012 COMMISSIONER ANDERSON OPEN MEETING SEPTEMBER 13, 2012, AGENDA ITEM NO 8; MEMO FROM COMMISSIONER ANDERSON
61 9/20/2012 PUC CADM ORDER
62 9/20/2012 PUC CADM OUTGOING COMMISSION SIGNED ORDER MAIL LOG
63 9/25/2012 EL PASO ELECTRIC COMPANY CLEAN COPY OF TARIFF