Filings for 40293



Case Style   APPLICATION OF SOUTHWESTERN PUBLIC SERVICE COMPANY TO ADJUST ITS ENERGY EFFICIENCY COST RECOVERY FACTOR

61 filing(s).

Item File Stamp Party Filing Description
6 4/6/2012 ALLIANCE OF XCEL MUNICIPALITIES MOTION TO INTERVENE
11 4/12/2012 ALLIANCE OF XCEL MUNICIPALITIES LIST OF ISSUES
24 5/1/2012 ALLIANCE OF XCEL MUNICIPALITIES REQUEST FOR HEARING
29 5/3/2012 ALLIANCE OF XCEL MUNICIPALITIES 1ST SET OF RFI TO SOUTHWESTERN PUBLIC SERVICE COMPANY
30 5/3/2012 ALLIANCE OF XCEL MUNICIPALITIES PROTECTIVE ORDER CERTIFICATIONS
48 5/22/2012 ALLIANCE OF XCEL MUNICIPALITIES RESPONSE TO SOAH ORDER NO. 3
39 5/15/2012 ALLIANCE OF XCEL MUNICIPALITIES 2ND SET OF RFI TO SOUTHWESTERN PUBLIC SERVICE COMPANY
12 4/13/2012 AT&T TEXAS COMMISSION STAFF'S 1ST RFI TO SOUTHWESTERN PUBLIC SERVICE COMPANY
7 4/9/2012 GOLDEN SPREAD ELECTRIC COOPERATIVE, INC. MOTION TO INTERVENE
5 4/4/2012 PUC CADM ORDER OF REFERRAL
17 4/20/2012 PUC CADM OPEN MEETING, APRIL 27, 2012; DRAFT PRELIMINARY ORDER
36 5/10/2012 PUC CADM ORDER REQUESTING BRIEFING ON THRESHOLD LEGAL/ POLICY ISSUES
37 5/11/2012 PUC CADM DRAFT AMENDED PRELIMINARY ORDER
27 5/3/2012 PUC CADM PRELIMINARY ORDER
28 5/3/2012 PUC CADM OUTGOING COMMISSION-SIGNED ORDER MAIL LOG
49 5/23/2012 PUC CADM AMENDED PRELIMINARY ORDER
50 5/23/2012 PUC CADM OUTGOING COMMISSION-SIGNED ORDER MAIL LOG
57 6/7/2012 PUC CADM PROPOSED ORDER
58 6/28/2012 PUC CADM ORDER
59 6/28/2012 PUC CADM OUTGOING COMMISSION SIGNED ORDER MAIL LOG
42 5/16/2012 PUC INFRASTRUCTURE AND RELIABILITY PROTECTIVE ORDER OF THERESE HARRIS
52 5/30/2012 PUC LEGAL STAFF'S BRIEF ON THRESHOLD LEGAL/POLICY ISSUES
40 5/16/2012 PUC LEGAL PROTECTIVE ORDER OF ADRIAN EISSLER
25 5/2/2012 PUC LEGAL STAFF 4TH RFI TO SPS: QUESTION NO. 4-1 to 4-4
38 5/14/2012 PUC LEGAL STAFF'S 6TH RFI TO SPS; QUESTION NO. 6-1 to 6-6
34 5/10/2012 PUC LEGAL COMMISSION STAFF'S 5TH RFI TO SOUTHWESTERN PUBLIC SERVICE COMPANY QUESTION NO. 5-1 TO 5-2
18 4/20/2012 PUC LEGAL 2ND RFI TO SPS QUESTION NOS. 2-1 to 2-4
19 4/26/2012 PUC LEGAL COMMISSION STAFF'S 3RD RFI TO SOUTHWESTERN PUBLIC SERVICE COMPANY QUESTION NO. 3-1
10 4/12/2012 PUC LEGAL COMMISSION STAFF'S LIST OF ISSUES
41 5/16/2012 PUC RATE REGULATION PROTECTIVE ORDER OF KRISTIN CAVIN
56 6/6/2012 SOAH SOAH ORDER NO. 4 : GRANTING MOTIONS TO INTERVENE; ADMITTING EVIDENCE; DISMISSING SOAH DOCKET; AND REMANDING CASE TO THE COMMISSION
20 4/26/2012 SOAH SOAH ORDER NO. 2: ADOPTING AGREED SCHEDULE
8 4/11/2012 SOAH SOAH ORDER NO. 1: CASE DESCRIPTION; REQUIRING PARTIES TO CONFER AND FILE; RESPONSIVE PLEADING DEADLINE; AND ENTRY OF A PROTECTIVE ORDER
31 5/7/2012 SOAH SOAH ORDER NO. 3: ADOPTING AGREED SCHEDULE
23 4/30/2012 SOUTHEWESTERN PUBLIC SERVICE COMPANY RESPONSE TO COMMISSION STAFF'S 3RD RFI QUESTION NO. 3-1
51 5/30/2012 SOUTHWEST PUBLIC SERVICE COMPANY BRIEF ON THRESHOLD LEGAL/ POLICY ISSUES
43 5/16/2012 SOUTHWESTERN PUBLIC SERVICE COMPANY RESPONSE TO COMMISSION STAFF'S 5TH SET OF RFI QUESTIONS NO. 5-1 AND 5-2
44 5/16/2012 SOUTHWESTERN PUBLIC SERVICE COMPANY CONFIDENTIAL- RESPONSE TO STAFF'S 5TH RFI STAFF EXHIBIT 5-1: BATE STAMP: 1-15
53 6/1/2012 SOUTHWESTERN PUBLIC SERVICE COMPANY Unoppposed Stipulation
54 6/1/2012 SOUTHWESTERN PUBLIC SERVICE COMPANY JOINT MOTION TO ADMIT EVIDENCE AND REMAND STIPULATED CASE
55 6/4/2012 SOUTHWESTERN PUBLIC SERVICE COMPANY Corrected Unopposed Stipulation
61 7/17/2012 SOUTHWESTERN PUBLIC SERVICE COMPANY CLEAN COPY OF TARIFF SHEETS
16 4/19/2012 SOUTHWESTERN PUBLIC SERVICE COMPANY RESPONSE TO COMMISSION STAFF'S 1ST RFI
26 5/3/2012 SOUTHWESTERN PUBLIC SERVICE COMPANY REQUEST FOR APPROVAL OF AGREED PROCEDURAL SCHEDULE AND DISCOVERY DEADLINES
32 5/9/2012 SOUTHWESTERN PUBLIC SERVICE COMPANY AFFIDAVIT OF PROOF OF NOTICE
33 5/9/2012 SOUTHWESTERN PUBLIC SERVICE COMPANY RESPONSE TO COMMISSION STAFF'S 4TH RFI
35 5/10/2012 SOUTHWESTERN PUBLIC SERVICE COMPANY RESPONSE TO THE ALLIANCE OF XCEL MUNICIPALITIES 1ST SET OF RFI QUESTIONS NO. 1-1 THROUGH 1-10
9 4/12/2012 SOUTHWESTERN PUBLIC SERVICE COMPANY LIST OF ISSUES IN RESPONSE TO THE ORDER OF REFERRAL
21 4/26/2012 SOUTHWESTERN PUBLIC SERVICE COMPANY RESPONSE TO COMMISSION STAFF'S 2ND RFI QUESTION NOS. 2-1 THROUGH 2-4
1 4/3/2012 SOUTHWESTERN PUBLIC SERVICE COMPANY (SPS) APPLICATION OF SOUTHWESTERN PUBLIC SERVICE COMPANY TO ADJUST ITS ENERGY EFFICIENCY COST RECOVERY FACTOR
2 4/3/2012 SOUTHWESTERN PUBLIC SERVICE COMPANY (SPS) DIRECT TESTIMONY OF JEFFREY L. COMER
3 4/3/2012 SOUTHWESTERN PUBLIC SERVICE COMPANY (SPS) DIRECT TESTIMONY OF J. DEREK SHOCKLEY
4 4/3/2012 SOUTHWESTERN PUBLIC SERVICE COMPANY (SPS) DIRECT TESTIMONY OF R. NEIL COWAN
15 4/18/2012 SPS REQUEST FOR APPROVAL OF AGREED SCHEDULE AND AGREED DISCOVERY DEADLINES
45 5/17/2012 SPS RESPONSE TO THE ALLIANCE OF XCEL MUNICIPALITIES' 2ND SET OF RFI; QUESTIONS NO. 1-1 THROUGH 2-4
46 5/17/2012 SPS RESPONSE TO COMMISSION STAFF'S 6TH SET OF RFI; QUESTIONS NO. 6-1 THROUGH 6-6
47 5/18/2012 SPS 1ST SUPPLEMENTAL RES;PONSE TO COMMISSION STAFF'S 6TH SET OF RFI; QUESTION NO. 6-3
14 4/16/2012 TEXAS DEPARTMENT OF HOUSING AND COMMUNITY AFFAIR'S WITHDRAWAL OF MOTION TO INTERVENE
13 4/13/2012 TEXAS DEPARTMENT OF HOUSING AND COMMUNITY AFFAIRS MOTION TO INTERVENE
22 4/30/2012 TEXAS INDUSTRIAL ENERGY CONSUMERS MOTION TO INTERVENE
60 7/9/2012 XCEL ENERGY CLEAN COPY OF TARIFF PAGES