Filings for 28834
Case Style APPLICATION OF SHARYLAND UTILITIES FOR A CERTIFICATE OF CONVENIENCE AND NECESSITY (CCN) FOR A 138-KV TRANSMISSION LINE IN HIDALGO COUNTY, TEXAS, TO IMPLEMENT A HIGH VOLTAGE DIRECT CURRENT INTERCONNECTION WITH COMISION FEDERAL DE ELECTRICIDAD
124 filing(s).
Item | File Stamp | Party | Item Type | Filing Description |
---|---|---|---|---|
1 | 10/31/2003 | SHARYLAND UTILITIES, L.P. | PL | SHARYLAND UTILITIES, L.P. REQUEST FOR A CCN DOCKET NUMBER FOR: APPLICATION OF SHARYLAND UTILITIES FOR A CERTIFICATE OF CONVENIENCE AND NECESSITY (CCN) FOR A 138-KV TRANSMISSION LINE IN HIDALGO, COUNTY (TEXAS) TO IMPLEMENT A HIGH VOLTAGE DIRECT CURRENT INTERCONNECTION WITH COMISION FEDERAL DE ELECTRICIDAD |
2 | 11/5/2003 | SHARYLAND UTILITIES, L.P. | PL | Sharyland Uitilites, L.P. CCN APPLICATION |
3 | 11/7/2003 | SHARYLAND UTILITIES, L.P. | PL | CORRECTION TO ATTACHMENT 3 |
4 | 11/12/2003 | PUC POLICY DEVELOPMENT | PL | ACKNOWLEDGEMENT OF RECEIPT; NOTICE OF APPLICATION FOR CERTIFICATE OF CONVENIENCE AND NECESSITY IN HIDALGO COUNTY, TEXAS; FILE NAME: 1110H.052 |
5 | 11/12/2003 | PUC POLICY DEVELOPMENT DIVISION | PL | ORDER NO. 1 REQUIRING INFORMATION FROM APPLICANT AND RECOMMENDATION FROM STAFF ON SUFFICIENCY OF APPLICATION AND NOTICE; ADDRESSING OTHER PROCEDURAL MATTERS |
6 | 11/12/2003 | PUC POLICY DEVELOPMENT DIVISION | PL | NOTICE OF APPLICATION FOR CCN IN HIDALGO COUNTY, TEXAS |
7 | 12/1/2003 | SHARYLAND UTILITIES, L.P. | PL | RESPONSE TO ORDER NO. 1 |
8 | 12/2/2003 | SHARYLAND UTILITIES, L.P. | PL | NOTIFICATION OF SHARYLAND UTILITIES, L.P. PURSUANT TO ORDER NO. 1 |
9 | 12/3/2003 | SHARYLAND UTILITIES, L.P. | PL | Sharyland Utilities, L.P.'s Proof of Notice By Mail and Proof of Publication |
10 | 12/8/2003 | PUC LEGAL | PL | COMMISSION STAFF'S RESPONSE TO ORDER NO.1 |
11 | 12/11/2003 | PUC POLICY DEVELOPMENT | PL | ORDER NO. 2: ADDRESSING SUFFICIENCY AND NOTICE; AND ESTABLISHING PROCEDURAL SCHEDULE |
12 | 12/12/2003 | SHARYLAND UTILITIES, L.P. | PL | SUPPLEMENTAL FILING WITH RESPECT TO NOTICE |
13 | 12/22/2003 | JOSE DE LA FUENTE | PL | COMMENTS |
14 | 12/23/2003 | JOHNNY HART | PL | REQUEST TO INTERVENE |
15 | 12/30/2003 | PUC LEGAL & ENFORCEMENT | RFI | STAFF'S FIRST SET OF REQUESTS FOR INFORMATION TO SHARYLAND UTILITIES, L.P. (AB1-1 TO AB1-14) |
16 | 1/8/2004 | PUC POLICY DEVELOPMENT | PL | ORDER NO.3 GRANTING MOTION TO INTERVENE |
17 | 1/8/2004 | PUC LEGAL & ENFORCEMENT | PL | REQUEST TO EXTEND THE DEADLINE FOR REFERRAL TO THE STATE OFICE OF ADMINISTRATIVE HEARINGS |
18 | 1/9/2004 | PUC POLICY DEVELOPMENT DIVISION | PL | ORDER NO.4; GRANTING REQUEST FOR EXTENSION OF DEADLINE FOR STAFF RECOMMENDATIN ON REFERRAL TO THE STATE OFFICE OF ADMINISTRATIVE HEARINGS |
19 | 1/20/2004 | SHARYLAND UTILITIES, L.P. | RFI | Response to Staff's First RFI |
20 | 1/22/2004 | PUC LEGAL | PL | STAFF'S MOTION FOR REFERRAL TO THE STATE OF ADMINISTRATIVE HEARINGS |
21 | 2/2/2004 | POLICY DEVELOPMENT DIVISION | PL | Order of Referral & Preliminary Order |
22 | 2/10/2004 | SOAH | PL | ORDER NO.6 NOTICE OF TELEPHONIC PREHEARING CONFERENCE |
23 | 2/18/2004 | SHARYLAND UTILITIES, L.P. | PL | PROPOSED PROCEDURAL SCHEDULE |
24 | 2/18/2004 | Sharyland Utilities | PL | CONTACT INFORMATION |
25 | 3/5/2004 | SOAH | PL | ORDER NO. 7 MEMORIALIZING PREHEARING CONFERENCE |
26 | 4/7/2004 | SHARYLAND UTILITIES, L.P. | TEST | Direct Testimony of Mark E. Caskey on Behalf of Sharyland Utilities, L.P. |
27 | 4/7/2004 | SHARYLAND UTILITIES, L.P. | TEST | Direct Testimony of Ralph G. Goodlet, Jr. on Behalf of Sharyland Utilities, L.P. |
28 | 4/7/2004 | SHARYLAND UTILITIES, L.P. | TEST | Direct Testimony of Rob R. Reid on Behalf of Sharyland Utilities, L.P. |
29 | 4/7/2004 | SHARYLAND UTILITIES, L.P. | TEST | Direct Testimony of Martin Baughman on Behalf of Sharyland Utilities, L.P. |
30 | 4/21/2004 | JOHNNY HART | PC | COMMENTS |
31 | 4/28/2004 | SHARYLAND UTILITIES, L.P. | PL | REPLY TO COMMENTS OF JOHNNY HART |
32 | 4/28/2004 | PUC LEGAL & ENFORCEMENT | PL | RESPONSE TO THE APRIL 21, 2004, COMMENTS OF JOHNNY HART |
33 | 5/10/2004 | SOAH | PL | ORDER NO. 8: CANCELING PREHEARING CONFERENCE |
34 | 5/19/2004 | SHARYLAND UTILITIES, L.P. | PL | STATEMENT OF POSITION OF JOHNNY HART INTERVENOR |
35 | 5/26/2004 | Sharyland Utilities | PL | JOINT MOTION OF SHARYLAND UTILITIES, L.P. AND COMMISSION STAFF TO ABATE PROCEDURAL SCHEDULE |
36 | 5/28/2004 | SHARYLAND UTILITIES, L.P. | PL | ORDER NO. 9 SETTING DEADLINE FOR RESPONSE |
37 | 5/28/2004 | PUC LEGAL & ENFORCEMENT | PL | LETTER TO CLARIFY THE REASON WHY STAFF REQUESTED AN ABATEMENTBEFORE FILING ITS TESTIMONY |
38 | 6/1/2004 | JOHNNY HART | PL | REPLY TO JOINT MOTION OF SHARYLAND UTILITIES, L.P. AND COMMISSION STAFF TO ABATE PROCEDURAL SCHEDULE |
39 | 6/2/2004 | PUC LEGAL & ENFORCEMENT | TEST | DIRECT TESTIMONY OF ALLEN S. BOLING, P.E. |
40 | 6/7/2004 | PUC LEGAL & ENFORCEMENT | PL | COMMISSION STAFF'S APPEAL OF ORDER NO. 9 |
41 | 6/9/2004 | SOAH | PL | ORDER NO. 10 : CLARIFYING ORDER NO. 9, POSTPONING HEARING ON THE MERITS AND REQUIRING CERTAIN FILINGS |
42 | 6/10/2004 | PUC LEGAL & ENFORCEMENT | PL | LETTER INFORMING THE COMMISSION THAT THE STAFF OF THE P.U.C. OF TEXAS (STAFF) IS WITHDRAWING ITS ORDER NO. 9 |
43 | 8/2/2004 | SHARYLAND UTILITIES, L.P. | PL | RESPONSE OF SHARYLAND UTILITIES, L.P. TO ORDER NO. 10 |
44 | 8/6/2004 | SOAH | PL | ORDER NO. 11 : LIFTING ABATEMENT AND RESETTING HEARING |
45 | 8/19/2004 | MCALLEN ECONOMIC DEVELOPMENT | PL | LETTER EXPRESSING SUPPORT OF THE SHARYLAND HVDC INTERCONNECTION PROJECT |
46 | 8/30/2004 | SHARYLAND UTILITIES, L.P. | TEST | Rebuttal Testimony and Exhibits of Nicolas Puga |
47 | 8/30/2004 | SHARYLAND UTILITIES, L.P. | TEST | Rebuttal Testimony of Rob R. Reid |
48 | 8/30/2004 | SHARYLAND UTILITIES, L.P. | TEST | Rebuttal Testimony and Exhibits of Ralph G. Goodlet, Jr. |
49 | 8/30/2004 | SHARYLAND UTILITIES, L.P. | TEST | Rebuttal Testimony of Martin Baughman |
50 | 9/7/2004 | SHARYLAND UTILITIES, L.P. | PL | STATUS REPORT STATING THAT A PREHEARING CONFERENCE IS NOT NECESSARY |
51 | 9/9/2004 | SOAH | PL | ORDER NO. 12 CANCELING PREHEARING CONFRENCE |
52 | 9/13/2004 | SHARYLAND UTILITIES, L.P. | PL | WITNESS LIST/ ORDER OF PRESENTATION (ATTACHEMENT A) AND EXHIBIT LIST (ATTACHEMENT B) |
53 | 9/13/2004 | PUC LEGAL & ENFORCEMENT | PL | ALL PARTIES PLAN TO PRESENT STAFF WITNESS AND STAFF EXHIBIT NO. 1 |
54 | 9/16/2004 | JOHNNY HART | PL | LETTER INFOMING WHAT THE INTERVENOR PLANS TO PRESENT AT THE SEPTEMBER 27, 2004 HEARING ON THE MERITS |
55 | 9/20/2004 | JOHNNY HART | PL | DESIGNATIONS OF ANTICIPATED LENGTH OF CROSS-EXAMINATION |
56 | 9/20/2004 | SHARYLAND UTILITIES, L.P. | PL | DESIGNATIONS OF ANTICIPATED LENGTH OF CROSS-EXAMINATION |
57 | 9/20/2004 | PUC LEGAL & ENFORCEMENT | PL | LETTER TO INFORM YOR HONOR AND ALL PARTIES OF RECORD THAT THE STAFF OF THE P.U.C. ANTICIPATES CONDUCTING THE FOLLOWING CROSS EXAMINATION AT THE HEARING ON THE MERITS |
58 | 9/24/2004 | SHARYLAND UTILITIES, L.P. | PL | LETTER STATING THAT SHARYLAND AND MR. HART HAVE AGREED THAT IT WOULD BE USEFUL TO DEFER THE HEARING IN THIS PROCEEDING CURRENTLY SCHEDULED MONDAY, SEPT 27 AND CONDUCT SETTLEMENT DISCUSSIONS TO SEE IF IT CAN BE RESOLVED |
59 | 9/28/2004 | SOAH | PL | ORDER NO. 14 CONTINUING HEARING ON THE MERITS AND REQUIRING A STATUS REPORT |
60 | 10/4/2004 | Sharyland Utilities | PL | STATUS REPORT |
61 | 10/6/2004 | SOAH | PL | ORDER NO. 15: CONTINUING HEARING ON THE MERITS AND REQUIRING A STATUS REPORT |
62 | 10/11/2004 | SHARYLAND UTILITIES, L.P. | PL | STATUS REPORT |
63 | 10/13/2004 | SOAH | PL | ORDER NO. 16 CONTINUING HEARING ON THE MERITS AND REQUIRING A STATUS REPORT |
64 | 10/15/2004 | KENNEDY REPORTING SERVICE | PL | PREHEARING CONFERENCE, TUESDAY, SEPTEMBER 21, 2004, 10:00 A.M., PAGES 1 - 19 |
65 | 10/18/2004 | JOHNNY HART | PL | NOTICE OF WITHDWRAWAL OF INTERVENTION OF JOHNNY HART |
66 | 10/18/2004 | SHARYLAND UTILITIES, L.P. | PL | STATUS REPORT IN ACCORDANCE WITH ORDER NO. 16 |
67 | 10/20/2004 | SOAH | PL | ORDER NO. 13: CONFIRMING TELEPHONIC FINAL PREHEARING CONFERENCE |
68 | 10/20/2004 | SOAH | PL | ORDER NO. 17: WITHDRAWAL OF INTERVENOR |
69 | 10/21/2004 | PUC POLICY DEVELOPMENT | PL | ORDER NO. 18: CONTINUING HEARING ON THE MERITS AND REQUIRING A STATUS REPORT |
70 | 10/25/2004 | SHARYLAND UTILITIES, L.P. | PL | STATUS REPORT |
71 | 10/26/2004 | SHARYLAND UTILITIES, L.P. | PL | PROPOSAL FOR THE HEARING ON THE MERITS TO BE HELD ON TUESDAY, NOVEMBER 9, 2004 AT 9:00 AM |
72 | 10/28/2004 | SOAH | PL | ORDER NO. 19: SETTING HEARING ON THE MERITS |
73 | 11/3/2004 | SHARYLAND UTILITIES, L.P. | PL | SHARYLAND WILL GO FORWARD WITH THE HEARING ON THE MERITS SCHEDULED FOR NOV. 9, 2004, AT 9 AM |
74 | 11/5/2004 | SOAH | PL | ORDER NO. 20: RELEASING WITNESS AND AGREEING TO PROCEDURAL FORMAT |
75 | 11/17/2004 | Sharyland Utilities | PL | COPIES OF SU EXHIBIT NO. 12 |
76 | 11/18/2004 | Sharyland Utilities | PL | CONSLUSION OF HEARING |
77 | 11/22/2004 | SOAH | PL | ORDER NO. 21: SETTING TELEPHONE CONFERENCE |
78 | 11/23/2004 | SHARYLAND UTILITIES, L.P. | PL | COPY OF THE JOINT AGREED EXHIBIT NO. 1 |
79 | 12/3/2004 | KENNEDY REPORTING SERVICE | PL | HEARING ON THE MERITS - TUESDAY, NOVEMBER 9, 2004, 9:05a (pages 1 - 236) |
80 | 12/10/2004 | KENNEDY REPORTING SERVICE | PL | TELEPHONIC POST-HEARING CONFERENCE TUESDAY, NOVEMBER 23, 2004 (PAGES 1-10) 10:06 A.M. |
81 | 12/16/2004 | SHARYLAND UTILITIES, L.P. | PL | SU AGREES TO A FURTHER EXTENSION OF THE STATUTORY DEADLINE FOR THE FINAL ORDER, TILL MARCH 31, 2004 |
82 | 12/21/2004 | SOAH | PL | ORDER NO. 22: ADMITTING JOINT EXHIBIT NO. 1 INTO EVIDENCE |
83 | 12/21/2004 | SHARYLAND UTILITIES, L.P. | PL | Proposed Findings of Facts, Conclusions of Law, and Ordering Paragraphs of Sharyland Utilities, L.P. |
84 | 12/21/2004 | SHARYLAND UTILITIES, L.P. | BR | Sharyland Utilities, L.P.'s Initial Brief |
85 | 12/21/2004 | SHARYLAND UTILITIES, L.P. | PL | SUBMITTAL LETTER FOR INITIAL BRIEF & PROPOSED FINDINGS OF ACT |
86 | 12/21/2004 | PUC LEGAL & ENFORCEMENT | BR | STAFF'S POST HEARING INITIAL BRIEF |
87 | 12/21/2004 | PUC LEGAL & ENFORCEMENT | PL | PROPOSED FINDINGS OF FACT |
88 | 1/13/2005 | SHARYLAND UTILITIES, L.P. | PL | LETTER TO INFORM CORRECTION OF TYPOGRAPHICAL ERRORS IN INITIAL BRIEF |
89 | 1/14/2005 | SHARYLAND UTILITIES, L.P. | BR | Sharyland Utilities, L.P.'s Reply Brief |
90 | 1/14/2005 | PUC LEGAL | BR | STAFF'S REPLY TO POST-HEARING INITIAL BRIEFS |
91 | 1/14/2005 | SHARYLAND UTILITIES, L.P. | PL | LETTER TO JUDGE SEITZMAN |
92 | 1/18/2005 | SHARYLAND UTILITIES, L.P. | BR | CORRECTIONS TO THE REPLY BRIEF |
93 | 1/20/2005 | PUC POLICY DEVELOPMENT | PL | KENNEDY REPORTING SERVICE -EXHIBIT INDEX |
94 | 1/24/2005 | SHARYLAND UTILITIES, L.P. | PL | MOTION FOR OFFICIAL NOTICE AND TO ADMIT LATE-FILED EXHIBIT INTO EVIDENCE |
95 | 1/27/2005 | CHAMBER OF INDUSTRY OF THE STATE OF NUEVO LEON | PL | LETTER URGING COMMISSION TO APPROVE SHARYLAND UTILITIES APPLICATION FOR A CCN |
96 | 1/27/2005 | SECRETARIA DE DESARROLLO ECONOMICO | PL | LETTER FROM ELOY CANTU SEGOVIA URGING COMMISSION TO APPROVE SHARYLAND UTILITIES APPLICATION FOR A CCN |
97 | 1/28/2005 | REYNOSA ASOCIACION DE MAQUILADORAS A.C. | PL | LETTER TO COMMISSIONERS SUPPORTING SHARYLAND UTILITIES IN THIS DOCKET |
98 | 2/4/2005 | LA SECRETARIA DE ENERGIA DE MEXICO | PL | LETTER TO COMMISSION |
99 | 2/7/2005 | SHARYLAND UTILITIES, L.P. | PL | ENGLISH TRANSLATION OF THE LETTER FILED ON FEB. 4, 2005 BY LA SECRETARIA DE ENERGIA DE MEXICO |
100 | 2/9/2005 | SOAH | PL | ORDER NO. 23: REOPENING RECORD AND ADMITTING SHARYLAND EXHIBIT NO. 13 INTO EVIDENCE |
101 | 2/14/2005 | SECRETARIA DE DESARROLLO ECONOMICO Y EMPLEO | PL | LETTER TO COMMISSIONERS |
102 | 2/15/2005 | SHARYLAND UTILITIES, L.P. | PL | ENGLISH TRANSLATION OF ITEM 101 FILED ON FEB. 14, 2005 |
103 | 2/15/2005 | CANACINTRA REYNOSA | PL | LETTER TO COMMISSIONERS |
104 | 2/16/2005 | CANACINTRA REYNOSA | PL | ENGLISH TRANSLATION OF ITEM 103 FILED ON FEB 15, 2005 |
105 | 2/18/2005 | SHARYLAND UTILITIES, L.P. | PL | LETTER TO ADVISE THAT THE TEXAS SUPREME COURT DENIED THE PETITION FOR REVIEW IN THE HAMMACK CASE |
106 | 3/10/2005 | SHARYLAND UTILITIES, L.P. | PL | LETTER CONCERNING THE STATUTORY DEADLINE |
107 | 3/18/2005 | SOAH | PL | Proposal for Decision |
108 | 3/21/2005 | POLICY DEVELOPMENT DIVISION | PL | Exception & Replies Memo |
109 | 3/22/2005 | SHARYLAND UTILITIES, L.P. | PL | LETTER AGREEING TO AN EXTENSION OF THE STATUTORY DEADLINE UNTIL APRIL 19, 2005 |
110 | 3/28/2005 | SHARYLAND UTILITIES | PL | LETTER STATING THAT SU RESERVES THE RIGHT TO FILE A RESPONSE TO ANY EXCEPTIONS THAT MAY BE FILED |
111 | 3/28/2005 | PUC LEGAL | PL | STAFF'S EXCEPTIONS TO THE PROPOSAL FOR DECISION |
112 | 4/4/2005 | SHARYLAND UTILITIES, L.P. | PL | Sharyland Utilities, L.P.'s Response to Staff's Exceptions to PFD |
113 | 4/4/2005 | PUC LEGAL & ENFORCEMENT | PL | REPLIES TO EXCEPTIONS TO THE PROPOSAL FOR DECISION |
114 | 4/7/2005 | PUC POLICY DEVELOPMENT DIVISION | PL | DOCKET HAS BEEN PLACED ON THE AGENDA OF THE OPEN MEETING SCHEDULED TO BEGIN AT 10:30 AM ON APRIL 13, 2005 |
115 | 4/8/2005 | SOAH | PL | OPEN MEETING; APRIL 13, 2005; ITEM 12; DISCUSSION AND POSSIBLE ACTION WITH RESPECT TO FINAL ORDER |
116 | 4/12/2005 | CHAIRMAN HUDSON | PL | OPEN MEETING, APRIL 13, 2005; ITEM #12 MEMO |
117 | 4/20/2005 | PUC POLICY DEVELOPMENT DIVISION | PL | Final Order |
118 | 6/28/2005 | SOAH | PL | LETTER TO OPD RE: RETURNED EXHIBITS AND TRANSCRIPTS |
119 | 8/31/2005 | PUC POLICY DEVELOPMENT DIVISION | EX | SU EXHIBITS #1-12 |
120 | 8/31/2005 | PUC POLICY DEVELOPMENT DIVISION | EX | PUC STAFF EXHIBITS #1-3 |
121 | 8/31/2005 | PUC POLICY DEVELOPMENT DIVISION | EX | JOINT AGREED EXHIBITS #1 |
122 | 8/31/2005 | PUC POLICY DEVELOPMENT DIVISION | EX | PHC 02/19/04; (1) TAPE |
123 | 8/31/2005 | PUC POLICY DEVELOPMENT DIVISION | EX | HOM 11/9/04; (4) TAPES |
124 | 12/21/2018 | CENTRAL RECORDS | PL | SENT OFFSITE TO THE STATE RECORDS CENTER 12/2018 |
Export to Excel |