Case Style PETITION OF LYTTON SPRINGS EXCHANGE FOR EXPANDED LOCAL CALLING SERVICE TO THE BASTROP, BUDA, ROCKY CREEK, LOCKHART, SAN MARCOS MARTINDALE EXCHANGES. PURSUANT TO SUBST. R. 23.49(c)
59 filing(s).
Item | File Stamp | Party | Item Type | Filing Description |
---|---|---|---|---|
1 | 1/25/1994 | LYTTON SPRINGS | PRJ | PETITION OF LYTTON SPRINGS EXCHANGE FOR EXPANDED LOCAL CALLING SERVICE TO THE BASTROP, BUDA, ROCKY CREEK, LOCKHART, SAN MARCOS MARTINDALE EXCHANGES. P |
2 | 1/27/1994 | HEARINGS | PRJ | ORDER #1 : ORDER SETTING PROCEDURAL SCHEDULE AND REQUIRING NOTICE |
3 | 1/31/1994 | GC | PRJ | MEMO TO GTE RE : NOTIFICATION OF PETITION |
4 | 1/31/1994 | GC | PRJ | MEMO TO SWBT RE : NOTIFICATION OF PETITION |
5 | 1/31/1994 | GC | PRJ | MEMO TO GUADALUPE VALLEY COOP RE : NOTIFICATION OF PETITION |
6 | 1/31/1994 | GC | PRJ | MEMO TO CENTURY TELEPHONE RE : NOTIFICATION OF PETITION |
7 | 2/7/1994 | ELAINE MICHNA | PRJ | REQUEST TO ADD THE LULING EXCHANGE TO PETITION |
8 | 2/8/1994 | GUADALUPE VALLEY TELEPHONE | PRJ | EXEMPTION FILING TO THEIR ROCKY CREEK EXCHANGE |
9 | 2/8/1994 | GC | PRJ | STAFF RECOMMENDATION |
10 | 2/14/1994 | HEARINGS | PRJ | EXAMINER'S ORDER #2 : ORDER NOTIFYING PETITIONERS AND PETITIONED EXCHANGES THAT PETITION IS DEFICIENT & SHOULD BE AMENDED TO INCLUDE... |
11 | 2/14/1994 | GUADALUPE VALLEY TELE COOP | PRJ | EXEMPTION FILING |
12 | 2/16/1994 | ELAINE MICHNA | PRJ | REQUEST TO DISREGARD LETTER ASKING TO BE ADDED TO PREVIOUSLY SUBMITTED PETITION |
13 | 2/23/1994 | GTE/CONTEL | PRJ | MOTION FOR EXTENSION OF TIMELINE |
14 | 2/23/1994 | HEARINGS | PRJ | EXAMINER'S ORDER #3 : ORDER REQUESTING CLARIFICATION |
15 | 2/24/1994 | HEARINGS | PRJ | EXAMINER'S ORDER #4 : ORDER GRANTING MOTION FOR EXTENSION OF TIME AND REVISING PROCEDURAL SCHEDULE AND TIMELINE FOR ADMINISTRTIVE |
16 | 3/7/1994 | GUADALUPE VALLEY TELE COOP | PRJ | AFFIDAVIT |
17 | 3/11/1994 | GC | PRJ | STAFF RECOMMENDATION |
18 | 3/14/1994 | HEARINGS | PRJ | EXAMINER'S ORDER #5 : ORDER GRANTING EXEMPTION & DISMISSING PETITION IN PART ONLY & NOTIFYING PETITIONING EXCHANGE THAT PETITION IS SUFFICENT |
19 | 3/31/1994 | GC | PRJ | STAFF RECOMMENDATION |
20 | 4/5/1994 | HEARINGS | PRJ | EXAMINERS ORDER #9: ORDER NOTIFYING PETITION COORDINATOR AND LOCAL EXCHANGE COMPANIES THAT PETITION IS SUFFICIENT AND ... |
21 | 4/12/1994 | GC | PRJ | PROPOSED PROCEDURES TO BE ADOPTED |
22 | 4/28/1994 | MCI | PRJ | PETITION FOR LEAVE TO INTERVENE |
23 | 5/24/1994 | HEARINGS | PRJ | ORDER #7 : ORDER RULING ON MOTION TO INTERVENE FILED BY MCI |
24 | 5/31/1994 | GTE/CONTEL | PRJ | SUBMISSION OF PROOF OF PUBLICATION ATTESTING TO COMPLETITON OF PUBLICATION |
25 | 6/24/1994 | GC | PRJ | STAFF RECOMMENDATION |
26 | 6/27/1994 | HEARINGS | PRJ | EXAMINER'S ORDER #8 : ORDER DISMISSING PETITION IN PART AND DIRECTING PETITIONING LEC TO FILE COST STUDY, IMPLEMENATION PLAN AND FEE SCHEDULE |
27 | 7/7/1994 | MCI | PRJ | WITHRAWAL OF INTERVENTION |
28 | 7/13/1994 | HEARINGS | PRJ | ORDER #9: |
29 | 7/27/1994 | CONTEL | PRJ | COST DOCUMENTATION & IMPLEMENTATION SCHEDULE |
30 | 8/8/1994 | HEARINGS | PRJ | EXAMINER'S ORDER NO. 10: GRANTING INTERIM APPROVAL |
31 | 9/1/1994 | HEARINGS | PRJ | ORDER #11 : APPROVING IMPLEMENTATION SCHEDULE |
32 | 9/2/1994 | GTE | PRJ | REVISED ATTACHMENT TO THE COST SUPPORT |
33 | 9/6/1994 | GTE | PRJ | TARIFF SHEET REFLECTING ELC SERVICE |
34 | 2/10/1995 | CONTEL | PRJ | MOTION FOR DELAY IN IMPLEMENTATION SCHEDULE |
35 | 3/7/1995 | HEARINGS | PRJ | ORDER #12 : ORDER DOCKETING AND NOTICE OF DOCKETING |
36 | 3/9/1995 | MS KIESCHNICK & MS MICHNA | PRJ | LETTER TO THE COMMISISON RE : EFFORT TO RESOLVE THE MOTION TO DELAY THE IMPLEMENTATION SCHEDULE |
37 | 3/14/1995 | HEARINGS | PRJ | ORDER #13 : ORDER REQURING RESPONSE FROM PARTIES |
38 | 3/21/1995 | ELAINE MICHNA | PRJ | LETTER TO JUDGE BIERMAN RE : GTE/CONTEL'S MOTION FOR DELAY ... |
39 | 3/22/1995 | HEARINGS | PRJ | ORDER #14 : ORDER REGARDING PROPER FILING PROCEDURES AND NOTICE OF FAXED RESPONSES BY PROJECT COORDINATORS |
40 | 3/24/1995 | SWBT | PRJ | RESPONSE TO ORDER #13 |
41 | 3/24/1995 | GTE | PRJ | LETTER TO JUDGE BIERMAN RE : RESPONSE TO EXAMINER'S ORDER #13 |
42 | 3/24/1995 | GC | PRJ | RESPONSE TO CONTEL'S MOTION FOR DELAY IN THE IMPLEMENTATION SCHEDULE |
43 | 4/7/1995 | HEARINGS | PRJ | ORDER #15 : ORDER REQUIRING GTE/CONTEL TO RESPOND TO GC'S PLEADING |
44 | 4/17/1995 | GTE | PRJ | RESPONSE TO ORDER #15 AND AFFIDAVIT OF GILBERT R BAILEY |
45 | 4/20/1995 | MS KIESCHNICK & MS MICHNA | PRJ | LETTER TO JUDGE BIERMAN RE : COMMENTS IN RESPONSE TO GTE'S RESPONSE TO REFERENCED ORDER |
46 | 5/3/1995 | HEARINGS | PRJ | ORDER #16 : ORDER REGARDING IMPLEMENTATION DATES FOR ELCS FROM THE LYTTON SPRINGS & DALE EXCHANGES TO THE PETITIONED EXCHANGES |
47 | 5/19/1995 | GINNIE KIESCHNICK | PRJ | LETTER TO JUDGE BIERMAN RE : REQUEST TO ACCEPT APPEAL |
48 | 5/25/1995 | GTE/CONTEL | PRJ | RESPONSE TO APPEALS |
49 | 5/30/1995 | HEARINGS | PRJ | LETTER TO ALL PARTIES RE : THE COMMISSIONERS HAVE VOTE NOT TO HEAR THE APPEALS OF ORDERS #16 & 23 |
50 | 6/6/1995 | MS KIESCHNICK & MS MICHNA | PRJ | MOTION TO RECONSIDER APPEAL |
51 | 6/13/1995 | HEARINGS | PRJ | LETTER TO ALL PARTIES RE : THE COMMISSIONERS HAVE VOTED NOT TO HEAR THE MOTION TO RECONSIDER THE APPEAL OF THE ORDERS |
52 | 6/20/1995 | HEARINGS | PL | LETTER TO MS. KIESCHNICK & MS. MICHNA RE: APPEAL OF ORDER 16 AND 23 RFI CONCERNING ELCS. |
53 | 9/12/1995 | HEARINGS | PRJ | ORDER #17 : DE-DOCKETING AND REQUESTING RECOMMENDATION FROM STAFF |
54 | 10/12/1995 | ELAINA MICHNA | PRJ | LETTER TO JUDGE WALKER RE : REQUEST FOR ORDER REQUIRING GTE & SWBT TO SUBMIT DETAILED STATUS REPORTS |
55 | 10/25/1995 | SWBT | PRJ | PROPOSED IMPLEMENTATION DATE |
56 | 7/1/1996 | GC | PRJ | FINAL FEES REPORT |
57 | 7/3/1996 | LEGAL ADMIN | PRJ | ORDER #18 : GRANTING FINAL APPROVAL AND SEVERING ISSUES RELATING TO EXCESS COST AND LOST REVENUE |
58 | 5/16/2006 | CENTRAL RECORDS | PL | FILE PURGED (5/11/06) |
59 | 7/11/2014 | CENTRAL RECORDS | PL | Book File |